HomeMy WebLinkAboutPublic Works Committee Minutes 02.19.2020Minutes
Public Works committee
Wednesday, February 19, 2020
Council conference room
Present:
Marvin Carter
Richard Herr
Don Nelson
Heidi Sparks, Committee Chair
Iry Wilke, Committee Vice -Chair
Kurt Markegard, Public Works Director
Meeting was called to order at 6:00pm.
There was no public input.
General Items:
Review and approved the January 20, 2020 minutes. Richard Herr made a motion to approve minutes, this was
seconded by Iry Wilke. Motion carried.
New Business:
The committee reviewed the Engineering Report from KU (attached). Things of note include:
• East Downtown Infrastructure Project- Bids have been received and will be presented to council at the March 3,
2020 workshop
• 2020 Pavement Maintenance- Bid Advertisement will be on February 27, 2020 rather than the date listed in
report
Old Business:
No old business to discuss
Other Items:
• A review of the Septic Dump Station Revenue for 2019 as well as January 2020. Reports attached.
• A review of the Emergency Call Outs since January 20, 2020 took place. The Emergency Call Out report is
attached.
Future agenda items:
o KU will be attending committee meeting to present Design Standards and Rules Update when
completed- possibly at March meeting
o Discussion of alley situation by IGA and the vacant lot by Taco Bell
Announcements:
Next meeting is scheduled for Monday, March 16, 2020 at 6:00pm.
Meeting adjourned at 7:00pm
Respectfully submitted,
Heidi Sparks, Public Works Chair
j -r
iI KLI
City of Laurel Project Status Update
February 15, 2020
WWTP Screw Press (KU #1804-00120)
Current Status:
O Warranty Inspection NLT August 2, 2020
WWTP Screw Pump "A" Replacement (KU #1804-0347, Task 6)
Reason for Project: This key component of the WWTP has failed and needs to be replaced asap
Project Scope: Replace screw press "A".
Current Status:
• Grouting is scheduled for March
Sanitary Sewer 112S Remediation (KU #1804-00122)
Reason for Project: Buildup of HzS within the WW collection system has led to deterioration of manholes
and other system components.
Project Scope: Complete the design and construction administration for the proposed air
injection/diffuser system to address HZS build-up within the system.
Current Status:
• Preparation of a Pilot Study Memo is ongoing
On -Call Professional Services (KU #1804-00347)
Project Scope: Services may include engineering, surveying, planning or government relations.
Current Status:
• None
East 6th Street Improvements (KU #1804-00121)
• Warranty Inspection NLT August 15, 2020
Page 1 of 4
ENGINEERING, REIMAGINED
-KLICity of Laurel Project Status Update <K!
February 15, 2020
Data and Asset Management (KU # 1804-00461)
Reason for Project: Consolidate infrastructure information
Project Scope: Assemble city infrastructure data into a single source, which can be used to track and
manage assets
Current Status:
• KU is progressing- Tentative Project completion 15 March
East Downtown Infrastructure Improvements (KU #1804-01309)
Reason for Project: Reconstruction and rehabilitation of streets, utilities and various other infrastructure
improvements including Washington Ave., Idaho Ave. and Ohio Ave. generally bound between E. Main
Street and E. 1st Street, as well as E. 1" Street generally bound between Washington Ave. and Alder Ave.
Project Scope: Preliminary engineering, design, bidding and construction.
Current Status:
• Work in progress
Tentative Schedule: February 13, 2020 - Bid Opening
March 3, 2020 - City Council Workshop
March 10, 2020 - City Council Awards Bid
Design Standards & Rules Update (KU # 1804-02569)
Reason for Project: Update old standards
Project Scope: Develop a set of cohesive and concise design standards for public improvements to help
facilitate reviews of new developments and ensure the public improvements are designed in the City of
Laurel's best interest.
Current Status:
• Drafts of the all sections of the manual are complete
• Final sections of streets are complete
2019 Pavement Maintenance (KU #1904-00230)
• Warranty Inspection NLT August 21, 2020
Page 2 of 4
ENGINEERING, REIMAGINED
A� City of Laurel Project Status Update
February 15, 2020
Laurel Planning Services (KU #1804-00554)
Reason for Project: KU has been retained to provide City of Laurel planning services as needed.
Project Scope: Planning services may include: subdivision, zoning, development, floodplain hazard
management, miscellaneous reviews and other related work. KU will prepare staff reports,
recommendations, and attend meetings upon request.
Current Status:
• Floodplain Management —Joint Application for improvements at Riverside Park will need to
be completed and a Floodplain Development Permit issued.
• Subdivision Review — Goldberg Sporting Estates- On hold
• Growth Policy Update — This project has just begun with coordination between the Laurel
City Planner and KU.
Riverside Park Campground (KU # 1904-00634)
Reason for Project: New campground in Riverside Park
Project Scope: Work consists of surveying and designing a new campground within Riverside Park.
Current Status:
• 90% docs submitted for review March 6, 2020
2020 Pavement Maintenance (KU #1904-01874)
Reason for Project: This continues the City's annual pavement maintenance.
Project Scope: This year's scope entails crack seal and chip seal on streets identified as a having a paser
rating of 6. This excludes the MDT designated Urban Routes.
Milestones:
• Bid Advertisement February 20, 2020
• Bid Openning, March 13, 2020
• Construction- April —July
• Substantial Completion -June
• Final Completion- July
Current Status: Design is on going
Page 3 of 4
ENGINEERING, REIMAGINED
�!
of Laurel Project rUpdate
February
Other (Votes and Information
Other potential projects have been identified during recent conversations between City staff and KU.
City Public Works staff and KU task leaders meet bi-weekly to discuss current and future projects. As
these are tentative, the timing and extent of KU's services are TBD, unless noted otherwise.
Anticipated FY20 Proiects
1. West Railroad Street Reconstruction- Proposal submitted
2. Water Storage Tank Recoat
3. Water System Planning
a. Master Plan Update (potentially update PER concurrently)
b. Booster station rehabilitation or replacement (task order forthcoming)
c. Water storage tank
4. Capital Improvement Plan (CIP) assistance —pending further direction from the City.
Other Potential Future Proiects
1. WWTP Archimedes Screw Rehabilitation
2. Examining engineer review of 3rd Party submittals to City
3. On-call government relations
4. West Side TIFF
5. School Lot
Page 4 of 4
ENGINEERING, REIMAGINED
Septic Dump Station for 2019
January
802.24
February
658.36
March
2134.52
April
1865.93
May
1164.28
June
2754.2
July
3122.08
August
3407.64
September
3724.76
October
2410.76
November
1628.88
December
1790.8
total
25464.45
Septic Dump Station for 2020
January 1506.96
February
March
April
May
June
July
August
September
October
November
December
total 1506.96
Emergency Call -outs for Public Works February 19, 2020 PW meeting
IMMUS MrOTOMOIn
2-1 Water turn off for a house fire Village Subdivision
2-1 Water Leak on a service line on Durland Ave.
2-7 Sand Streets
2-9 Elm lift station alarm
2-13 Emergency locate and street closure for hit power pole East
Railroad Street