HomeMy WebLinkAboutPublic Works Committee Minutes 08.19.2019MINUTES
CITY OF LAUREL
PUBLIC WORKS COMMITTEE
MONDAY, AUGUST 19, 2019
A Public Works Committee meeting was held in the Council Chambers and called to order by
Committee Chair Mountsier at 6:00 p.m. on August 19, 2019.
COMMITTEE MEMBERS PRESENT:
_ Emelie Eaton _x_ Heidi Sparks
x Bill Mountsier Marvin Carter
x Dan Koch
x Richard Herr
OTHERS PRESENT:
Kurt Markegard, Public Works Director
Public Input: None.
General Items
Approve Minutes of July 15, 2019, Public Works Committee meeting. Heidi made the
motion to approve the minutes and Richard seconded the motion. Roll call was taken
and all voted in favor of the minutes.
New Business
Kurt explained that there was no emergency call out to report on so there is was no new
business to discuss.
Old Business
2. Set date for Open House. Kurt gave the committee an update on the water treatment
plant progress and he feels that the area is safe enough to hold the open house. Kurt
asked if everyone wanted to try to hold it the same night as a City Council Workshop at
5:30pm. Heidi informed the committee that the dates for the City Council Workshops
in September are changing. The only workshop in September will be on the 17'h. Bill
asked Kurt how long it would take to tour the water plant improvements and Kurt stated
that it would only take about 45 minutes. Kurt thought that would give the Council
members the time to get back to City Hall and attend the workshop meeting. Dan
indicated that he could make it on the 17`x' as well. The committee recommended that
the open house take place on the 17th of September at 5:30pm.
3. Engineering Reports- Kurt informed the committee about the work Great West
Engineering has completed recently. The wetland monitoring for the new intake lines
were recently completed. Kurt explained that in some areas you cannot even tell that a
water line has been installed. This report has been delivered to the Mayor and
forwarded to Robert Cole at the Army Corps. Great West Engineering is also working
with Cop Construction to take care of some of the punch list items for the new
sedimentation basins. Kurt informed the committee that the new sedimentation basins
are operational and the new intake is providing the water to the basins. Kurt explained
that the water is being feed into the new process by gravity from the new intake. Bill
asked if CHS Refinery is also being feed by the new intake and Kurt explained that they
are on raw water from the 2003 intake. CHS Refinery quit taking settled water a few
months ago because the river cleaned up. The Water Plant Chief Operator told Kurt
that they are having to feed a third of the chemical that they normally had to compared
to the old sedimentation basins. Kurt was glad that the process is going well but there
are still a few things that need to be completed with the software that run the valves and
pumps. Kurt said the fencing is also about completed.
KLJ Engineering has been working of a few projects and Kurt went through the
attached report on the progress of those projects. The sludge dewatering and digester
cleaning is complete. The City can now dry sludge coming out of the digesters and haul
it directly to the landfill. The drying beds may have to be used in the winter if the
temperatures are too cold though. Kurt informed the committee that a screw pump
replacement was needed due to a bent shaft. The cost for the pump is expensive. KLJ
Engineering will seek out quotes or bids from contractors to replace the pumps as the
City does not have the equipment to do the work. The screw pump will not be delivered
until the end of October. Kurt showed a small video of the bottom of the screw pump
and how the connections bolts are coming loose. The H2S remediation project has a
meeting with a chemical supply company the first week in September. Kurt explained
that this company is claiming to be able to help prevent H2S from forming in the
pressurized sewer main coming from the Village Lift Station on East Main Street. Kurt
should have more information after that meeting. Kurt informed the committee that the
East 6tl' Street Project is almost complete. Dan asked if the paint stripping was going to
be complete before school started. Kurt said that the painting will need to wait for the
asphalt to cure so the paint will stick. Heidi said that the street looked great and she
wished that we could do a project like that on the South Side streets. Kurt stated is
would be nice to rebuild S.W. 4"' Street from the Railroad Tracks to S. 8t" Avenue. The
East Downtown Infrastructure Improvements are in design and Kurt would like to get
the business owners and the lot owners in the area to discuss the proposed
improvements. The chip seal project is completed and Kurt explained that he was
informed that a fog seal had been put over the rock chips in order to keep the chips in
place. It also cuts down on the dust typical with a regular chip seal application. Heidi
thought it was a good idea as people's car windshields will be spared rock chips. Kurt
stated that this process is starting to be used by the State DOT and the City of Billings
as well. Riverside Campground task orders have been received by the City from the
Department of Justice. The task order for designing the campground will be going to
the next Park Board meeting for discussion. Kurt is hopeful that the new campground
could be open by next Memorial Day Weekend. Richard said that camping should be
allowed now that there are bathrooms in Riverside Park. Kurt said that the task orders
for the design from KLJ and the DOJ will be taken to the City Council in September.
Other Items
No items
Announcements
4. The next meeting on September 16, 2019 was discussed. Kurt asked the committee if
they wanted to have the open house and the next meeting two days in a row. Bill asked
if there was going to be any items to discuss and Kurt indicated that right now there was
not much going to be taking place except for pavement repairs. Bill asked the rest of the
committee members if there was any reason to meet in September. The committee
discussed not having the meeting but left it open that if they really need to meet that
they would hold one. Dan said that he was ok will going to the open house and
canceling the meeting. Heidi and Richard also agreed to not hold a meeting in
September unless one was needed.
The meeting was adjourned at 6:45pm
Submitted by Kurt Markegard
Attached; Engineering Reports from KLJ and Great West Engineering
City of Laurel, Montana
"On -Call" Engineering Contract
Great West Project No. 2-07128 and 2-14114
Date: August 19, 2019
To: Kurt Markegard, Public Works Director — City of Laurel
From: Chad E. Hanson, PE
Subject: Project Progress Update
The following sections summarize the current status and recent progress on active task orders
under our "on-call" engineering contract with the City. Please let me know if you have any
questions and/or would like more information.
��_�� l• r l.j � lei,.
Amy Chadwick completed the third and final wetland monitoring included in our scope of work,
and the report was forwarded to Robert Cole at the Army Corps of Engineers on the City's behalf.
This completes our work under this task order.
Task Order No. 29 — Phase 3 Water System Improvements
The project is substantially complete, and the contractor, COP Construction, is working on the
miscellaneous punch list items for final completion. The new sedimentation basins are fully
operational and performing well within the design parameters. The NTU of the water coming off
the plate settlers is below 1.0, and chemical usage is a quarter to a third of historical usage based
upon discussions with the plant operators.
i
KL)`l1. City of Laurel Project Status Update
August 1.5, 2019
lhlWrP Screw Press (KU #1804-00120)
Project Manager: Travis Jones/Doug Whitney
Reason for Project: The City's WWTP does not currently have adequate sludge handling equipment,
which has led to overfilling and backup of the drying beds, digesters, and various other WWTP
components. Completion of this project will allow for improved operations and allow for
maintenance of the digesters, which cannot be taken offline until this project is completed.
Project Scope: Design and construction of a new screw press to process WWTP sludge.
Milestones:
• Preconstruction meeting was held December 13, 2018
• Notice to Proceed will be January 7, 2019 (150 -day contract)
• Start-up of the sludge press and cake pump June 13, 2019
Current Status:
• Submittal process is underway
o Submittals are up to date
o PWTech submittal received February 11, 2019
• RFIs are up to date.
• Sludge dewatering is completed, and dewatering subcontractor has moved off site.
• Digester B has been drained and cleaned.
o Repair work on digester B have been completed.
■ Change Order No. 2, for these repairs, has been presented to the Council.
o Digester B has been returned to service.
o Contractor has made a claim for additional pumping.
■ Change Order No. 1 for the undisputed amount has been presented to the
Council. The disputed amount will be negotiated at a later date.
• Digester A has been drained and cleaned.
o Contractor is preparing to sand blast interior.
o Inspection and repairs will take place after sand blasting.
o Recoating of the interior will take place after the repairs are completed.
o Contractor has made a claim for additional pumping. This is currently under review.
• One sludge transfer pump has been removed.
o Both transfer pumps are on site.
o Installation of one of the pumps is underway.
■ A Work Directive for a replacement pressure sensor has been prepared.
• The blasting and repairs inside digester A have been completed.
• The sludge press and cake pump are operational.
• Operator training has been conducted.
• Substantial Completion has been issued and the Contractor is working on the punch list
items and project close out.
Page 1 of 8
ENGINEERING, REIMAGINED
KL)City of Laurel Project Status update
August 15, 2019
WWTP Screw Pump "A" Replacement (KU #1804-0347 Task 6)
Project Manager: Doug Whitney
Reason for Project: This key component of the WWTP has failed and needs to be replaced asap
Project Scope: Replace screw press "A".
Milestones:
• The City has order the Screw pump from the manufacture.
• KU has drafted a Quote package for the installation of the screw pump.
Project Manager: Doug Whitney
Reason for Project: Buildup of H2S within the WW collection system has led to deterioration of
manholes and other system components.
Project Scope: Complete the design and construction administration for the proposed air
injection/diffuser system to address H2S build-up within the system.
Milestones:
• Sewer sampling plan submitted to the City
• Sewer samples collected on July 19, 2018
• Results of sewer sampling received on July 30, 2018
• Analyses of sampling and recommendations for a second round submitted on August 3, 2018
• Second round of samples collected on August 14, 2018
• Second round of sampling results received on August 27, 2018
• Results of second round of sewer sampling received on September 25, 2018
• H2S monitoring: April 2-19, 2019 - Completed
• Recommendation from Manufacturer: week of June 3, 2019
• Draft Updated TM with cost estimate: June 10, 2019
• 60% Plans and Specs: June 28, 2019
• 100% Plans and Specs: July 12, 2019
• Advertise for Bid: July 16, 2019
• Bid Opening: August 6, 2019
Current Status:
• City has requested that KU proceeds with improvement design independent of future
sampling.
Page 2 of 8
ENGINEERING, REIMAGINED
di City of Laurel Project Status Update
August 15, r
1777T, '174
Project Manager: Carl Jackson
Reason for Project: This continues the City's annual pavement maintenance. As a result of significant
freeze -thaw during the 2017-18 winter, several City streets have significant pavement damage.
Project Scope: The 2018 scope is hot mix asphalt for repaving West 4t" Street (61' Ave. - 8t' Ave.) and
pothole repairs on West Railroad Street.
Milestones: Construction is complete. Striping was completed May 9-10.
Current Status: Final close out has been submitted for City signature as well as the final payment
application and reconciling change order.
Project Manager: Carl Jackson
Reason for Project: Street reconstruction between 1st Ave. and Wyoming Ave. to address failed
pavement, saturated subgrade conditions and surface runoff improvements. UPDATE: the scope
recently changed to include new water main from Pennsylvania to Wyoming.
Project Scope:
• Grading, paving, parking, and drainage enhancements (minor water main in Wyoming)
• Special Improvement District (sidewalks, driveways), pending approval
• Safety improvements
• Water main from Pennsylvania to Wyoming, including the Wyoming intersection valves.
Milestones:
• Bidding —April/May 2019
• SID creation — May/June 2019
• Construction —Substantial Completion walkthrough on August 15, 2019
Current Status: Construction is substantially complete. Final completion to be done before school
begins.
Page 3 of 8
ENGINEERING, REIMAGINED
City of Laurel
Project Status Update
August 15, 2019
Project Manager: Matt Corcoran
Reason for Project: Reconstruction and rehabilitation of streets, utilities and various other
infrastructure improvements including Washington Ave., Idaho Ave. and Ohio Ave. generally
bound between E. Main Street and E. 1st Street, as well as E. 15t Street generally bound between
Washington Ave. and Alder Ave.
Project Scope: Preliminary engineering, SID creation, design, bidding and construction.
Milestones:
• Survey & Geotechnical fieldwork —complete
• SID creation —Summer/Fall 2019 (tentative)
• Design & Bidding — Full bid package ready in January 2020
• Construction — May 2020
Current Status: Design is in -process and KU is expediting plans and specifications to start the
bidding/construction sequence as soon as possible. Bidding schedule may be delayed if
decisions by the City on out -of -scope work and funding are delayed.
Pavement Management Plan Update (KU #1804-01970)
Project Manager: Bryan Vanderloos
Reason for Project: Develop an updated pavement management plan (PMP) including MDT and City
streets within the Laurel corporate limits. This will be used for prioritizing the City's annual
pavement maintenance projects, along with satisfying MDT's requirement that the City update
its PMP on a regular basis to be eligible for certain future State funding.
Project Scope: Conduct a field inventory by assessing paved streets utilizing the Pavement Surface
Evaluation and Rating (PASER) methodology. A rating of 1-10 will be given to each road segment
based on distresses such as cracks, ruts, potholes, etc. Known roads that have failed pavement
sections and are in disrepair will not be evaluated, and simply given a poor rating.
Milestones:
• Final edits are complete, and the final draft was given to Kurt and Matt.
Final comments from the City are pending City's and MDT's review of the updated
recommendations.
Current Status: Once we have received final comments from the City and MDT, we will finalize the
report.
Page 4 of 8
ENGINEERING, REIMACINED
KL)City of Laurel Project Status Update
August 15, 2019
Project Manager: Bryan Vanderloos
Reason for Project: This continues the City's annual pavement maintenance.
Project Scope: This year's project entails crack seal, chip seal, pavement markings, and other
miscellaneous items on the following streets: South Washington Avenue; 5th Avenue from West
Main Street to West 2nd Street; Cottonwood Avenue from East Main Street to the Ditch
Crossing; East 8th Street from 1st Avenue to Pennsylvania Avenue; and Pennsylvania Avenue
from East 8th Street to East Maryland Lane.
Milestones:
• Bidding — complete
• Construction — April -June 2019
Current Status: Substantial competition walkthrough was don the week of August 12th, punch list for
final completion is forthcoming.
Project Manager: Matt Corcoran
Reason for Project: Repairing pot holes and other pavement damage caused by previous winter
freeze/thaw
Project Scope: Work consists of pothole and pavement restoration work in various locations
throughout town. Location will be flexible and determine in cooperation with Public Works staff.
The contract bid documents will be written in such a way so that quantities can be increased or
decreased depending on the City's budget.
Milestones:
• Design and Bid Document Preparation — Complete
• Bidding — Complete
• Pre -Construction Meeting—August 21St
• Construction Notice to Proceed —August 26th (35 day contract)
Current Status: Bids were received, and the project was awarded to FirstMark Construction. Bids
were under the initial budget, KU will work with City to increase quantities and cover more
areas within the budget.
Page 5 of 8
ENGINEERING, REIMAGINED
r
KQ
City of Laurel Project Status Update
,August 15, 2019 <<
Riverside Park Campground (KU # 1904-00634)
Project Manager: Matt Corcoran
Reason for Project: New campground in Riverside Park
Project Scope: Work consists of surveying and designing a new campground within Riverside Park.
Milestones:
® Design and Bid Document Preparation —ASAP
® Bidding — ASAP
® Construction — ASAP (goal is to be ready for next season)
Current Status: The task order was forwarded to Alicia Stickney with the State on 7/23 and have not
heard back on any comments.
Project Manager: Carl Jackson
Reason for Project: This contract would enable KU to provide consulting services that are not part of
an approved task order. Generally, this would apply to situations where KU's fees are small
enough that a separate task order is not necessary, or for time -sensitive matters.
Project Scope: Services may include engineering, surveying, planning or government relations.
Milestones: (as needed)
Current Status:
• During the 5/14 bi-weekly meeting KU was asked to evaluate funding options for the future
West Railroad Street reconstruction project. We'll work with City leadership to agree on the
planned approach to this, before proceeding.
Page 6 of 8
ENGINEERING, REIMAGINED
Project Manager: Forrest Sanderson
Reason for Project: KU has been retained to provide City of Laurel planning services as needed.
Project Scope: Planning services may include: subdivision, zoning, development, floodplain hazard
management, miscellaneous reviews and other related work. KU will prepare staff reports,
recommendations, and attend meetings upon request.
Milestones: (as needed)
Current Status:
Floodplain Management —Joint Application for improvements at Riverside Park will need to be
completed and a Floodplain Development Permit issued.
Subdivision Review — KU Staff are available to assist as necessary.
Zoning — KU Staff are available to assist as necessary.
Riverside Park Campground (KU#1904-00634) —The project will be transferred to Mike Bender
for design and management where Forrest has a regulatory role as City Floodplain
Administrator. Forrest will remain as project liaison between City and Project Manager.
Page 7 of 8
ENGINEERING, REIMAGINED
` City of Laurel Project Status Update
August 15, 2019
! r r
Other potential projects have been identified during recent conversations between City staff and
KU. City Public Works staff and KU task leaders meet bi-weekly to discuss current and future
projects. As these are tentative, the timing and extent of KU's services are TBD, unless noted
otherwise.
Anticipated FY19 Proiects
1. West Railroad Street coordination
2. Water System Planning
a. Master Plan Update (potentially update PER concurrently)
b. Booster station rehabilitation or replacement (task order forthcoming)
c. Water storage tank
3. Review of development rules and regulations (related to public works and planning)
a. Task order planned for FY20 (on hold)
4. Updating City utility maps and GIS
a. Task order planned for FY20 (on hold)
5. Capital Improvement Plan (CIP) assistance —pending further direction from the City.
Other Potential Future Proiects
1. WWTP Archimedes Screw Rehabilitation
2. Examining engineer review of 3rd Party submittals to City
3. Lion's park grant application assistance
4. On-call government relations
5. West side groundwater remediation
Page 8 of 8
ENGINEERING, REIMAGINED