HomeMy WebLinkAboutLaurel Airport Authority Minutes 03.28.1995LAUREL AIRPORT AUTHORITY March 28 , 1995
The meeting was called to order at 7:10 P.M. by Chairman John Smith.
Members present were ; Roy Zahm , Bob lestern , Dick Clayton , Bill3rennan
Guests _oresent were ; Frank Wagner , Max Castagne , Craig Canfield , Art Moshinskie ,
Sol Lovas ? ,LeRoy Monson , Gorvan LeDuc , Bob Roods , Rich McKamy ,
,
James L. Bon ?? , Ted Iverson , Alan Bentley , John Lowry
Bob Redding , Don Crilli , Rob Engh
Minutes of the February meeting were approved as read.
Bills presented were ;
K.K.1M. Faster plan update 972.00
Frar'-c Wagner copies 19.95.
Yell.Vall.Elec. power for March 95.55
*:orthern Skies Av. gasoline - snowplow 77.72
;loved by Western to pay bills , seconded by Clayton.Motion carried.
Craig Canfield of H.K.M. presented a Faster Plan update Two alternative plans for
expansion were discussed.A copy of the two plans are included with these minutes.
Bob Roods asked permission to build a 60 1 hangar in the new hangar area."otion was
made by Clayton to O.F. construction,seconded by Western.Motion carried.
The question was asked about how long Dave Powers will be able to lease a hangar
site without building a hangar.Chairman Smith will contact him and determine his
intentions.
Bob Redding would like us to read and approve or whatever his proposed Airport
Rules manual by our next meeting.
Meeting adjourned at 5:35 P.M.
Bi11 Bpe
Secretary
f Laurel Master Plan Update AIP--02
Preliminary Planning Estimate
Construct 3,800 Runway
Alternative No 1 - Relocate existing runway 240 feet to the north, Existing runway would'
be converted into a taxiway. Assumes future 1,00(1 foot extension to the southwest and an
ultimate 400 foot extension toi the narthSt.
ITEM QUANTITY UNIT UNIT PRICE TOTAL COST
1. Land Acquisition
Fee Acquisition 40 Acres 800.00 $32,000.00
Easement Acquisition 2 Parcel 5,000.00 $10,000.00
Appraisals & Negotiations 1 L.S. 13,400.00 $13,400.00
2.Earthwork & Drainage 350,000 C.Y. 2.00 $700,000.00
3. Pavement Section 43,300 S.Y. 18.00 $779,400.00
4. Electrical
MIRL 1 L.S. 100,500.00 $100,500.00
PAPI 1 L.S. 25,000.00 $25,000.00
5. Miscellaneous
Revegetation 1 L.S. $28,500.00 $28,500.00
Fencing 1 L.S. $13,400.00 $13,400.00
Pavement Markin 1 L.S. $20,100.00 $20,100.00
Total Alternative 1 $1,722,300.00
Federal Share (90%) $1,550,070.00
Sponsor Share (10%) $172,230,00
Alternative No'2 -- Relocate existing r-..n 5 feet to the north in order to provide
required separation distance between T/w C and the runway. Assumes a future 1,000
foot extension to the southwest and an ultimate 4,00 foot extension to: the northeast.
ITEM QUANTITY UNIT UNIT PRICE TOTAL COST
L Land Acquisition
Fee Acquisition 12 Acres 800.00 $9,600.00
Easement Acquisition 2 Parcel 5,000.00 $10,000.00
Appraisals & Negotiations 1 L.S. $13,400.00 $13,400.00
2.Earthwork & Drainage 125,000 C.Y. 3.00 $375,000.00
3. Pavement Section 28,000 S.Y. 18.00 $504,000.00
4. Electrical
MIRL 1 L.S. $100,500.00 $100,500.00
PAPI 1 L.S. $25,000.00 $25,000.00
5. Miscellaneous
Revegetation 1 L.S. $28,500.00 $28,500.00
Fencing 1 L.S. $13,400.00 $13,400.00
Pavement Markin 1 L.S. $19,000.00 $197000.00
Total Alternative 2 $1,098,400.00
Federal Share (90%) $988,560.00
Sponsor Share (10%) $109,840.00
FADATA\02\M201108WSTPLN.W K3
28--Mar-95