HomeMy WebLinkAboutResolution No. R19-34. ; foe ! I. $. . , is �.. EMI Lei 12 W41 F WHEREAS, the City of Laurel planned and publicly advertised the project known as the WWTP Sludge Dewatering Facilities Project, and the City awarded the project to Strategic Construction Solutions; and WHEREAS, City equipment failed during the project which required contractor to perform additional work, including additional equipment as explained in the attached Change Order Documents, and such unanticipated work and additional equipment resulted in an increase to the cost and number of days required for contractor's completion of the contract; and WHEREAS, the City's Engineers, KLJ, prepared the attached Change Order No. 3 and has determined the additional work and equipment requires an extension of the contract term and cost which are both necessary, reasonable, and in the City's best interest. NOW, THEREFORE, BE IT RESOLVED, the City Council hereby approves the attached Change Order No. 3 and authorizes the Mayor to execute it and all necessary documents on the City's behalf BE IT FUTHER RESOLVED the City Council authorizes both the increased cost and term of the contract as detailed and provided in the attached Change Order No.3. Introduced at a regular meeting of the City Council on July 16, 2019, by Council Member Sparks. PASSED and APPROVED by the City Council of the City of Laurel this 10h day of July 2019 APPROVED by the Mayor this 16`h day of July 2019. CITY OF LA L 11 Tlt6mas C. Nelson, Mayor W Bethany Wng,`Clerk-Treasurer, Clerk -Treasurer Approved as to form: ;�J Sam Painte , ivil City Attorney R19-34 Approve Change Order No. 3: WWTP Sludge Dewatering Facilities Project I �--wfcyizs Ctr iL� "'I f7;E- L'o A Ho' 3 Date of Issuance: Juno 21, 2019 Effective Datc: V,"VVI'll Slu-dge Degar atering lCiv,,ner: City of Laurel Contr"-Icl: 1 1se Bid Lmnlp Surr, Prica rens--K tor. Strut egic OW11,21-'s , to of Contract: ' 11/16/2018 Fnghreer'�, h ojul No,: 1804-00120 The coniract Docunleilts arc modified as folimms upon execution of dli°� Change 01 der: Chdilj�;(.Qr ikL i ,a roved additional -iption of Worl included car f o,ind i i Oi -C o �e .Dire Civ 2 and ('01.1 esporlding attachrnent As pat t ofthis Ch we, 0i -fei v i addiLio! tal 21 (L be added to io I time for dewatering and overall Contract Time. -------- -- - ------- - ----------- Attachnients (list doctiments supporting change): Frigineer's letter of recornn;endation dated Jane 21, 2019, and Work Change Directive No 2. Contractor's revised Clair) PCO 42/02 CHANGE IN CONTRACT" PRICE: Original comiral"t price: =k__2 .5_75 70 ).Q0_ Int tease from pieviously approved Change Orders No. 0 to No. 2-: Contract Price prior to r1his Change Ordcr: Increase of this Change Order: Contract Price incorporating this Change Order: CHANGE IN CONTRACTI'll'VIES: Ciriginal Contract Times: ❑ Working days FA, Calendar days Substantial (Dewatering) compleJor-, (days): 1 0 4, Ready for final payment Ways): 3 N Increase ft a i n 1) 1 Lviously approved Change Orders No, 0 to No. 2: Substantial {Dewatering) completion (days). 32 (41) Ready for final payment (days): 0 WA) Contract Times prior to this Change Order: Substantial (Dewatering) completion (days): 182 (86) Ready for final payment (days): 3 f Increase of this Chan, -,e Order: Substantial (Dewatering) completion (days): Ready for final payment (days): Contract Times with all approved Change Orders: Substantial (Dewatering) completion (days): 203 (107) Ready for final payment (days): 30 INN — ------ - R E C 0 1`0 AA E N D E D: ACCEPTED: ACCEPTE,9: By: By-' '4 En.ginear.(A-6thorized Signature) Owner (Aut prized griature) Contrzir"tor (Authorized Signature) Date. 2- -5 Z Date: Date: MYTP sludge Di?v.,aterinf., Facilities Change Order- No. 3 Page 1 of 1 KU Project 1.804-00120 znno"b'ARoad " auI gs,^AT S9 102-/329 |uxe2l.Z019 Tim Reiter Uh|kVNants SuAehniendent diyofiauro| P830«I0 LaureLKvI[3"O14 Ru: VKVVTPS|udDeDcaateringFacUides—[hanCeD/de/0o.3,EnOinee/sRecnmman6at|ao'Kevised DparTirm. As per section, 10.OS A. of the Montana Public Works Standard Specifications (MPWSS) General Conditions', this letter is to serve ds the Engineer's recon-Irnendation for the proposed' Charge Order (CO) 3.Theo/ighna|c|aimwasnzreivedbytheEngineer(KU)hnmtheConirac0nr(SC3)onAprilZb'2019.Tbis revised recommendadonisafollow uptothe ne�odatpdresolution during oorJone14,2O19meeting. Theo�Qinaidaimsobmittedbythe Contractor reque�edanadditinna(S3Z'49S76and 12days be added to the Contract due to additional Work and materials needed to clewater Digester A once the owner's pumps stopped working. On April 4"', the Ovvner issued VAlork Change Directive 2 instructing the Contractor to provide manpower ' and equipment butransfer the Sludge from Digester Ainto Digester B. Payment to be made on actual time and materials Plus the Contractor's Fee (CF) for the effort needed to transfer the sludge until the sludge level reached the 'Lop of the cone in Digester A On IMay 29, 201.9, the Engineers recommendation included a Contract Price increase of $23,750.62 and' the Contract Tirne be increased by 21 day5. This recoininendation excluded small tools, Midway 10K forklift and SCS trucks 325 and 362. The Contractor disagreed with the Engineer's recommendation. 0o]unel4,ZO19,amee\inQmascooducLe6atOtyHaUbetoecntheOwner,Controctnrondihe Frigineer. The disputed items were discussed, and all parties agreed to include the forldift and trucks in the Change Order. This revised Engineer's recommendation includes a Contract Price increase of ,�30,344.7Gand aContract Time increase nf21days. The additional Contract Price includes Contractor's labor cosT, Contractors equipment cost (rninUS small tools), bonds, Contractors Fee as stated in MPWSS's General Conditions Section 12.01.C, and Gross Receipts Tax (196). Please review our revised Engineer's Recommendation for Change Order No,3 for an increase in Contract Price of $30,344.76 and an increase in Conti -act Time of 21 (lays. The recommended increase of Contract Time is for the entire project as well as the clewatering portion of the project with no changes Lothe Contract Time for Final Payment. [han8ectothe VVyJTPDevvoterin@Facilities Project would beas smG/wc[n|wo. Rc|mAG|wco Original Contract Price $1,575000.CO |noeoseinContract Price from [O2 �26,17104 |ncreaseinContract Price from CO2 $11,758,11 Powntial Increase in Contract Price From 1,03 $30,344,76 Substantial Original Contract Time 150 Days lncreasein[untaaciTimehomCOI ODxyz hnuuase in[on1nsctTinnekmm[[)2 32 Days Potenda!Increase inCon( ill ( CD� 21 Days Final Contract Time 203 Days Dew��dnJ 4SDays gDays 32 Days 21Days 107 Days 0 Feel heetuountac{usUyoohaveaoyadditiona|guestionsorwouid|iketoreques(anyaddiUona| muie/a| be provided. Sincerely, KU ~.~ uo Whitney, PE--'' rnyeccEngmecr Enclosure(s): Proposed [hon.geOrder 3with attachments Project 4: 1304-00120 cc: Te,rySutherland, File EwG|wssn/wC. n[|m^C|wEn i' i i i- is � 1 ,, � 'I A� o 11 " C h � -� ; -, . � c� !I' k-,� c i i �,s " : : AW ion NAW brOwl Won hod hemin W pruned CA AM K fd coo of Ow w"AA wuu A: it I ink Q :4 Praltmol duys, X pix crMy ro anydon Mul Wou Oca 1._s _i prior zo moin; rr chwpv. w Qnusc� AW :md Contral ! him.. BiriMod change Ni COMMU Me NO CNO VA 1 AM: InWhOA Mv b"Junk Mac W, Odw. "No C"Ns MWUM No 2 Ngo 1 at 1 111 POM VIA VIQIT� lj� j,' 11 y 1 PHCAAO: Odw. "No C"Ns MWUM No 2 Ngo 1 at 1 111 POM VIA VIQIT� S(IS 4,'C,(' E SouThC'm Avn I'd c s a, A z cj t s a ,"- 2 W1 6 Phane, "'48c1 Egel-''400 PGO :W002 Project: SGSIMC271, if, -&"S - I-aurd VVVVI P Sludge r3;tirai4r ng 15190. Laurel, Montana 59C'44 Primie 0mitrac-A Potetitial Change Order -#002.- Change orderft-2 Primary Digester Sludge Ret-m.-wal i'll-J F R 0 Mr Strategic' Con'siruckc,l) Solutions 26 11 G Rd, 4700 E. Sout'wrn Ave Billinus, Nlnl)t--)na !1914; fvlosa Arizona. 35206 IG CONTRACT: 10 1, - - Laurel VIXTrP Sludge tic vvatorirg Facilities Prime Gcmtrrict RI.-ClUEST RECEIVLD FROM: STATUS: r�r oft 1 NUMIMIlum FIELD Cl IANGE: No LOCATION: Prinary'rank SCHEDULE IMPACT. CREATED BY: CREATED DATE: PRIME CONTRACT CHANGE ORDER: ACCOUNTING METHOD: PAID IN FULL: William morall (SCS) 41261201�i None Amount Based No TOTAL AMOUNT: $30.344.76 POTENTIAL CHANGE ORDER TITLE: Change oder 42 Priniary Digester Sludge Re. moval C14ANGE REASON: No Chance Reason POTENTIAL CHANGE ORDER DESCRIPTION: (7he Contract Is Changed As Follows) City's pump. could not transfer the sludge out of the digester causing alternate methods of removal cf the sludge out of the diceslet Remnoval of small tools created a deduction of x2:151.76. ATTACHMENTS: a 0, ,,d' Ala Cos! Cane: Dcscription Type Arnaunt NO, 01-0.01 011- Vmnge Oder 2 00,1 Enqjie, - 9 HPS L,)bw "'X1;1.14.._, , 1, -)NS S(IS 4,'C,(' E SouThC'm Avn I'd c s a, A z cj t s a ,"- 2 W1 6 Phane, "'48c1 Egel-''400 PGO :W002 Project: SGSIMC271, if, -&"S - I-aurd VVVVI P Sludge r3;tirai4r ng 15190. Laurel, Montana 59C'44 Primie 0mitrac-A Potetitial Change Order -#002.- Change orderft-2 Primary Digester Sludge Ret-m.-wal i'll-J F R 0 Mr Strategic' Con'siruckc,l) Solutions 26 11 G Rd, 4700 E. Sout'wrn Ave Billinus, Nlnl)t--)na !1914; fvlosa Arizona. 35206 IG CONTRACT: 10 1, - - Laurel VIXTrP Sludge tic vvatorirg Facilities Prime Gcmtrrict RI.-ClUEST RECEIVLD FROM: STATUS: r�r oft 1 NUMIMIlum FIELD Cl IANGE: No LOCATION: Prinary'rank SCHEDULE IMPACT. CREATED BY: CREATED DATE: PRIME CONTRACT CHANGE ORDER: ACCOUNTING METHOD: PAID IN FULL: William morall (SCS) 41261201�i None Amount Based No TOTAL AMOUNT: $30.344.76 POTENTIAL CHANGE ORDER TITLE: Change oder 42 Priniary Digester Sludge Re. moval C14ANGE REASON: No Chance Reason POTENTIAL CHANGE ORDER DESCRIPTION: (7he Contract Is Changed As Follows) City's pump. could not transfer the sludge out of the digester causing alternate methods of removal cf the sludge out of the diceslet Remnoval of small tools created a deduction of x2:151.76. ATTACHMENTS: a 0, ,,d' SCS page 1 of 4 Printed On: 611 E/2019 09:57 ANI Cos! Cane: Dcscription Type Arnaunt NO, 01-0.01 011- Vmnge Oder 2 00,1 Enqjie, - 9 HPS L,)bw S7C,3,1,0 NIA 0 01-0,301 2 - Chan, -,,a 0fdar 2 Za-ch Sultp-;land - 5 HRS Lator 1428.03 2 - Change Oder Jascn Les?ie; - 9 KRS Later '442A0 r OMor Tru -N:125 Equipment W144.L10 5 WA W00,202 Chan4eOrder 2 lrjck 16' Dit.ir, r, -w 1744.30 fr CIA. 0120,0M2 -Change Order 2 1 C K rc,'V4t Equipment $2%M 7 MA 2- Oiamis Ordti 2 Hy,N,,J--Puuy EqLk "Wlt 128260 8 N 7A fY.*,C4,X 2 - Change: 02yer 2 fivd:.IJr Pump Dtl3,.e?l, El WA 2 - Change Order 2 0m, Er, 7q--,im 8 Ic NA 00Q-CX,'l - Chang e Odu 2 Jascn Leih_r 8 La-lor 1435,S0 I I WA 2 - ChangL Order 2 Labor 140219 12 NIA0,-;t! 2 Chanqc, r)dcr'-! 'XV? T P,p RrentaA NIA 2 Ra -n FaR�:)! C ,G5s,"er Eqpiiul S5 i-11 I I Ch2r,',0 O.,,Ur 2 t.t7way 1") K porklet 42w:.00 I E NIA ^ 2 chm]e. Ordu 2 fnlc� '-"25 SCS page 1 of 4 Printed On: 611 E/2019 09:57 ANI PGO 11-111002 SOS p8,ge 2 of 4 Pralled On: 6112/2019 09:57 AM !ililiR ..------- - -- ------- ----- 1 2'! Orc �f 2 S --G 0 2 --- - ------ ------ 2, C uct�: 1! �j 2 Fj Grhnr'l• "3rid .-i 2e 1 is ZI "Z-�t 2, N �ilt 2 h1 i 0,13 G2.J-2 C,:u qE, 0 2 N -A fl +. chi-qa- 2 xi%'�Tl "HI/Ita-Al Fa 'p Crm�!rit a, C 'h"no" '* 2 R fv R I r. wnr AII 2 ch'.4r� 0 da 2 8�1 C)Ihf- COC-COC-2 - 01,1e, 2 ollwf 322 2 - 2, DIx, E!'Q ,,S N;A P'X:.2 Ghn"Ige 2 Jzj;:,n L,-ilte; 8 h4is Lab::r e3d84r, NN"A C' c') 2 C 0' 2 7a --h 115,j -s i-at';r N Ch irgn 0 -dc, 2 525.0,1 t ay i tVA G'X,-GW-Z - Chxipe Cdv 2 Xljle'Tl M fll;° :;.rd h -,WPI Fqulf'm: n! 3�K F(I 2t, Nf�l CIX cj,.,o 2 - Char,r-l-&r 2 Ral, 4 Rent Cro-50',rf LqLirxma,, SSIA I tVA .<.., w"d 31,2 41 NIA ccc-'n'2 - O'der 2, Cron Erg' -"J:. -ie:u5431 GC' X4%30,2 - 'C,h�ngz 0�du 2 jascn 5 Ha�rl Lam- NVA 2 Zach SUIela,ld 8 Hcurs Lnccr S321.681 10 k Fc,44i"I E'liip-nent 323.O.00 NtA C( 0'0.2 Cflan?o Older 2 xyl'lm pul;p NA CC�-'-r-00.2 - Ch'I;e 2 R F"" R "'Cs'ao'er Eav'pncnl S51.41 4? NIA IanpC'mjt, 2 Tc'chs 325 anj W2 1286.Gg 4B NIA MC-C=X;2 - C�Izlmja 0-jE, , .r U -z"Ju I 10 Ho�zf!; Don Em- s LMmr -3 1 l.ea 4 4� Ni.•i 00,04..,-,_s.2 - Charlie 0:rfer 2 Jason Lesrt, T Hours L-gtDr S368"10 �-r NIA 011dl* - 2a -h Sz jthc' f3rxl lofl"Ays Uatrw 3321.58 5 NIIA 2 - Change 0.&7 2 Trs ,s,325 3,J r2 Fqup�,ent SZ. c.50 N"A lz:-Caa 2 - C; ange Ode` 2 t i-; a a VK Equipient 5 WA ct'anle O'Je7 2 xytt-':'l Punp S262.60 54 NtAk C,0�2�€:2:'2.2 - C'iange G:de-, R i -Cr H cxcrsoller EqJJYILn! $61,41 Or Wlk C?�anie OnJc� 2 Don 'is I ku's Laz3or 5.549.- Alm UC',�,a2-Cnanp',A -2 sulhcria-'d "o abor 5'i NIA 2 Cf-.irrlr: 2 jamm [ o;hp, 10 Hmuf.. I-ah"'r 3485'5o C�'Uqc 0114c� 2 Tia6,,,, �25 and 3n"7 Eq6pqmnt S?rR i'11-0 -5 NVAQC'Z-C"0"2 - Ctlaag" 2 ki ..way ICK fc*,Vt 60, W A c anis' auef 2 xpaT PC n1p, Eq6pn,,,'lt S2 2.60 C, I MIA C& -C,2-0.2 -f gnge Cl.der 2 R :"C- R C'Fcf"s":"ar C' w INA CranqOrder 2 Don, Eng,-,jisl A Hajrs i Labx C,', NA -'n"' 0,1'- a acEl,rsur.pterlstt 8 H"turs La-�' SOS p8,ge 2 of 4 Pralled On: 6112/2019 09:57 AM C',IA,)'k0[,J!, s c IS page 3 of 4 Printed On: (3/18,120191 09:57 AM - --------- ---- --- A Wt ( Ir S a 2 u T, n! J, 0 R FR ---------- - --------- 2 - -- --- ------ ----- --- - ----- i'l 2 - C !ID 1 ..1 k ,3 ."j. tj Ord,, - "b."r 4 NIM 9-- A"A R tC' P r.iss,-vc- ilr J ('A" situ 2,1. C 0 Cf 0, D- 2 - ch "w"its 0Ar 15ll';- P 0 CX,sr 3 WA D� JLi E., NIf", 2 i (310 S25.C-0 OCO, 0,1-0,2 - Gnj,={e 04,ft7 2 i 5 ll^t P U19, I_En 2 G.{,e 2 vkrds 52J,(JJ �17 Nbl, C,al�2 1 `4 RT Llikler S2L., OD CaiaCrdc- 2 l5tl> P a 0 Orar 2} ar .z FCO NIA OT,du* 2 15 1,!, P & �. 2 a NO, -Clarme Orjo,- 2 Uh-r 52,',Co S2 KYA 0,iw 2 1 7 O�har S25 r0 A4 NiA CCO Or.it: 2 S;", P & 0 SS WIA Bds S2SX0 CIa7,gc ()!Jt- 2 CR7 525.0 Ef7 W", Od,,- 2 5 'A-, P & 0 - - 533;',c0 uJ N, A C-CM-CCO1.2 - Cnn,4- Orlv 2 ao!"n Gher - ------- - S2 9.0 W'A, O:C64�C(1,9 -C,nng2 OrAr-2 71� C R S29,Cr) Nil. ONG00, 2 - Ordr 2 -,1 P 0 C. C -2-C. 3;._-, 0 1 J 2 Doi Enqq.,i�t 10 Icurs Lobw S�39,5c OrJe* 2 Jascm tcs.,,er IC, Acas La hl r i4F,5.,A ;A, C -.CC - C,)al'-,gl� O,Je� 2 'W 'i� Siulh,�;�ird Z Libor }:IIT Ci -v O,,le7 2 7,. -Cis 325 n n, ZS 2 Equ:Pmuml S, 8, 0 WA C"Iar:OL, O,jt- 2 Midway I(X EqupmenA 0 ----------------- Of; e, 2 Xy!,am. ;',kj rp Eq,,,, rxmorz s c IS page 3 of 4 Printed On: (3/18,120191 09:57 AM NiA R at r ----------- p C, . .... .. .... 5 P 0 ........ . . .... ....... — ------- — -- OA N C, h, C,cl, 2 Sis rnI iu—, L abT ys N 0..r, C'CC,2 - Clti T,w Z su1,�, ,,, 6 H i N" NIA C"nTTp C,;,filt x 7,-Jci, 32and3__ Fa;;If m,: A 12e8 60 MIA Cq,ipne,.! Z2"112J'Irli Ch -U, Oo ;!, r MAy U -I", rte: rliii S250 12TA".1n, A 0, d'r - R Fc,- R Yu !zwn :5!A I r.., jF� cmif! r t P^refs 0!er S22.C(j cnnngn O'ClLr i GRT QT1. S 21, 71-1—=c subtoti.1; $."rl 344,7C Grand Total:10,344�1(i j Doug Whitney (KLJ) KLJ Strategic Construction Solutions 2611 Gabel Rd, 261', Gabel Rd. 4700 E. Southern Ave Billings Wcrltana 59102 1311ings l0entana 59102 Mesa Arizona 852C6 SIGNATURE DATE SIGNATURE DATE SIGNAWRE SGS page 4 of 4 Printed 0.,1: 611812019 09,57 AM DATE