HomeMy WebLinkAboutPublic Works Committee Minutes 05.20.2019Minutes
Public Worbs Committee
May 20, 2019 6:00 P.M.
Council Conference Room
Those present:
Matt Corcoran, KLJ-City Engineers
Kurt Marhegard, 5taff Advisor
Emelie Eaton, Chair
Karl Dan Koch
Marvin Carter
Bill Mountsier
Richard Herr
Heidi 5parbs
The meeting started at 6:00. There was no public in attendance.
General items
1. Review and approve minutes of March 21, 2019 meeting. The
minutes were reviewed. Richard Herr moved the minutes be
approved as written. K. Dan Koch seconded.
2. Emergency Call Outs. There had only been five call outs since
those reviewed at the March meeting. On March 19 the water
at 2414 Lackrawanna was shut off due to a leakz. On March 22
the backwash pond at the Water Plant needed pumping out
because the ice went out in the river. On March 24 the pump
at the Water Treatment Plant was moved because they had
filled the spot they were pumping to with mud. On April 18 the
water was turned on at 2618 Topekza. On May 8 there was a
sewer issue at 1220 Fourth Avenue which turned out to be a
homeowner problem and not a City issue. There had been no
after hours water breaks and issues that have arisen are being
dealt with during the day for the most part.
New Business
3. Report on City wide cleanup
This item was on the agenda because Chairwoman Eaton had learned
several constituents were misunderstanding the City's role in this cleanup
effort. Public Worbs Director Marbegard stated that as long as he has
been an employee of the City there has been participation in a spring
citywide cleanup. He stated it started with Jean Carrol Thompson and she
coordinated with Bright and Beautiful. Then a few years bacb Vi Hills
began coordinating the event and worked with Laurel Churches and
received some help from Bright and Beautiful. The Public Works Director
then recited the amounts of garbage that had been taken in during the
one day event which included 10 forty yard containers that had been filled
and 32 tons of materials that were hauled to the Billings landfill. When it
was expressed that certain citizens thought that the City was going to go
up and down every alley pickling up garbage left beside containers and
emptying the garbage cans the Public Works Director stated that the
City's participation is limited to the four employees who go down the alleys
and pick up what has been requested to be picked up (people need to
call in ahead of time and a work order needs to be completed), the
organization of those work orders and the organization of the employees
by staff, the payment of the cost to haul 32 tons of material to the Billings
landfill; and the waiver of fees at the Laurel container site for City
residents. Richard Herr stated that it is his recollection that in 2006 Vi Hills
began organizing the clean up and coordinating with churches; that he
has participated in cleanup efforts with his church and that individuals
from churches also used to help haul away garbage left in alleys. Mary
Carter stated that the effort was advertised on the bottom of the City
water bill. Bill Mountsier stated that the assumption was that if
advertisement is printed on a City document it is a City project; which does
not help alleviate the confusion that was being discussed. K. Dan Koch
stated that he had failed to call in a request to have a tree stump hauled
off but had attached a note to which stated: "Please Take Me". He stated
that indeed, someone had taken the note and left the stump. The Public
Works Director stated that the church groups were painting curbs and
cleaning up under the underpass as participation in a "Day of Caring". He
stated that the City will be hosting the fall clean up where residents have
the opportunity to put out bags of leaves, branches and mostly yard
debris. He cautioned that various locations in Laurel have been
experiencing an outbreak of bed bugs. He cautioned everyone to NOT
handle other's mattresses, chairs or couches. These are to be picked up
with a backhoe to protect individuals and limit the spread of the bugs.
4. Grain Silos
This item was on the agenda because Committee Chairwoman Eaton had
heard various rumors already spreading about what the land was going to
be used for. Public Works Director Markegard stated that the property
next to Hardees where the grain elevators stood is still a part of the Sam
McDonald estate. The estate had applied for an Asbestos Certified
Demolition Permit as well as a Large Grant from the TIF District and that
the time to use the Large Grant monies was expiring. He stated that First
Markt was the contractor for the project, which only included tearing down
and hauling away the silos and building that were on the property. He
stated the City has not received any documents for a new building; the
property has not been sold; there will NOT be a round-about going in at
the top of the underpass and there are approach permits that are being
looked at for access onto the property. Several committee members stated
the work was excellent and the site looped much better now. Bill
Mountsier inquired about the age of the buildings. Both the Public Worbs
Director and Emelie Eaton had done research on this topic and the brief
summary is that the original wooden flour mill was built somewhere
between 1903 and 1908. In The Centennial, written by Gay Easton and
Emelie Eaton, there is a photograph of that flour mill in the far
background of a picture taken from atop the water tower that used to be
in what is now Thompson Parr. In approximately 1935 that flour mill
burned to the ground and the current metal and concrete buildings were
put in its place on May 28, 1956 by Ken Hagemann.
5. Water and Sewer Maps and Design Standards for Public Worlgs
Infrastructure
Public Works Director Kurt Markegard introduced Matt Corcoran from
KLJ, the City Engineering firm. Kurt stated that in 2003 an Intern was
hired to gather infrastructure information. This information was then
compiled in 2008 by Great West Engineering and are the maps that the
City uses currently. Unfortunately, much of the information has not been
updated and many times City crews will arrive on a job and have
incorrect information regarding the size of the pipe they will be working
on; whether the pipe is PVC or cast iron; and in some instances even the
location of the pipe or whether the pipe actually exists have been wrong.
It would save the City a lot in lost worktime to have the correct
information for crews. Matt Corcoran stated that in Billings the
information is all on-line and layers of information can be added or
removed telling about information like pipe size all the way to distance
from a STOP sign. The Public Works Director stated this is a project being
planned for the next fiscal year which will not begin until July 1, 2019. Bill
Mountsier stated he could certainly see how updated maps could save City
crews time. The Public Works Director stated that crews have learned to
show up to a job with parts they anticipate will be needed. However,
recently they have not had correct information and have turned to former
City employees, now retired for as long as 12 years, to rely on their
knowledge. Heidi Sparks asked Matt Corcoran how long he thought it
would take to compile computer friendly maps. Matt Corcoran replied
that it would take approximately three months if all the information is
correct. He stated that they have the data but need to update it with
recent projects and what has been identified as incorrect. He stated that
the newer projects will provide better information. Heidi inquired what a
GSI online subscription would cost. {Matt Corcoran stated they cost
between $100 to $500 depending on how many layers the City wants to
add and that the software allows as many as five users online at any time.
Both K. Dan Koch and Heidi Sparks inquired as to who would confirm the
pipe size and verify its location. The Public Works Director relayed that he
had recently discovered some lost paperwork which he thinks will help fill
in much of the incorrect information. He stated that there are blueprints
that fill in a 20 year gap of lost information about Special Improvement
Districts. Chairwoman Eaton made a motion stating the Public Works
Committee approves of and supports KLJ's proposal to gather all the
information and maps now in existence from all the various sources and
compiling it into an online format for use by City crews. Heidi Sparks
seconded the motion. The motion was unanimously approved.
The Public Works Director then moved the committee on to the second
half of this agenda item. He produced the Standards for Public Works
Improvements for the City of Laurel, Montana and the Rules and
Regulations Governing Utility Services and Streets The committee was
well familiar with both of these publications after having been familiarized
with them most recently when discussing an issue of xeriscaping on
boulevards and what the City could or could not do to enforce perceived
violations. The committee was well aware of the need to update both
documents. Matt Corcoran stated that the time frame to update both
documents would be approximately five months, if approved as a budget
item. Thus, work would not begin until after July 1 and then a draft would
have to be presented to Council and staff would also have a chance to
have additional input. Heidi Sparks inquired about making homes
retroactively have people conform to the new rules. The answer is that the
City could not make someone redo their yard or boulevard but any new
work done would have to conform to the new standards. Karl Dan Koch
stated that this would help with the City wide problem of putting in
culverts instead of drains. Richard Herr relayed that the culvert near his
home has only increased over time and homes still get flooded. The Public
Works Director relayed a story about a relatively new business that
learned the importance of proper drainage. Heidi made a motion stating
this committee fully supports and approves of KU s efforts to update both
the Standards for Public Works Improvements for the City of Laurel,
Montana and the Rules and Regulations Governing Utility Services and
Streets. Chairwoman Emelie Eaton seconded the motion which was
unanimously approved. Public Works Director Kurt Markegard stated
that he sincerely appreciates that Matt Corcoran is working on behalf of
the City and has the City's best interested in mind with these projects.
Old Business
6. Engineering Reports
The May 17, 2019 Project Progress Update Memorandum from Great West
was supplied to all members and reviewed first.
A. The first item in that document is the "New Water Intahe", which the
Public Worbs Director stated was dealing with the wetland restoration.
The memo states that Great West needs to supply the Army Corp of
Engineers with additional information. The City needs to continue to
monitor the length of the pipeline to make sure the grasses are continuing
to grow. The City did purchase wetland grass seed for planting in bald
spots.
B. The second item was "Water System Improvements". The Public Worlgs
Director stated that new plate settlers should arrive tomorrow, May 21,
2019. He stated that 70 degree temperatures are needed for the mastic to
cure. Crews will be trained in June on the new equipment, how it functions
and how to wort with it. Kurt would likte to have a tour of the new site on
July 23rd for the entire committee as well as the full Council. Richard Herr
questioned whether that meant that the new Sed Basins will be online and
providing water to the refinery. The answer is that they are currently.
C. The third item was "Water System Improvements" which discusses
lowering the 2003 intakze and supplying raw water to the refinery. As was
stated in the previous item discussion, raw water is currently being supplied
to the refinery.
Kurt had supplied copies of KLJ's May 15, 2019 City of Laurel Project Status
Update
WWTP Screw Press/Digester Rehabilitation
The Council will vote tomorrow, May 21, 2019, to approve Change Orders 1
& 2 which will pay for unanticipated extra works already performed. The
Update states that the screw press is scheduled for shipment on May 16th
and the Public Worbs Director stated that it should be in Laurel at any
time.
H25 Remediation
Two rounds of samples were collected last summer. The area was
monitored for H2S in April of this year. It is anticipated that with all the
data received a solution should be agreed upon by late next month and
the project should go out to bid by mid-July. When questioned about the
suspected high H25 from BNSF the committee was told that, as per the
previous discussion, the City's Rules and Regulations Governing Utility
Services and Streets are out of date and there is no recourse the City has at
this time. At present the City has to asks BNSF for permission to come on its
property and tape samples. If high readings continue to be present in
these samples the City can only asks BNSF to help.
2018 Pavement Maintenance Project.
The Committee was referred to "Other Notes and Information" in
reference to the frost heaves throughout the community. Current
estimates are over $415,000 to repair what has been identified.
East 6t" Street
June 10 has been identified as a potential start date with a 60 day
construction contract so the project will finish by the time school starts.
Richard Herr inquired as to whether there would be a driveway approach
because the map of the project did not show one. The response was that
there would be a driveway approach. Herr then inquired as to whether
the millings from the current street couldn't be used to male repairs
throughout town. The response was that millings from E. 6t" Street are not
going to be of good quality would not benefit another project.
LURA Infrastructure
The Public Worbs Director stated that he is going to request KLJ change
the name of this project as there is a lackz of support from the TIFD
committee but that the Mayor has instructed Staff that this project will
move forward. Richard Herr stated that at the LURA meeting earlier
today that committee chair stated that the taxes are paid by the
businesses throughout the district and that they do not see why their tax
money should be spent on three East End streets. The Public Worlgs
Director stated that the taxes are paid by everyone in the district, not just
businesses and that the three streets in question are in the TIF District and
will specifically help businesses with sidewalks, approaches and streets.
K. Dan Koch inquired as to timing. It was reiterated that the Mayor has
stated this project will move forward and the SID is hoped to be created
by late summer or early autumn.
Pavement Management Plan
This is in draft form and is being reviewed by Public Works Department.
2019 Pavement Maintenance
Work is expected to run through June, 2019.
On-Call Professional Services
Much of this information referenced handing projects over to the new City
Planner, Nick Altonga.
Laurel Planning Services
Much of this information referenced handing projects over to the new City
Planner, Nick Altonga, from New Hampshire, who has been hired as the
City Planner. Nick has a degree in Planning. Richard Herr inquired
whether Riverside Park would be open by Memorial Day. The Public
Works Director stated that was his intention but since Memorial Day
weekend is this weekend, he was not certain. He stated that this
bathroom, up by the boat ramp, was the first of three bathrooms that are
planned for Riverside Parks. All need to be above flood plain. The current
flood plain is approximately 16 inches below the floor of the current
bathroom. Richard Herr then inquired as to whether the current (old)
bathroom could be used as a shelter to show off some of the historical signs
in the part as it would only need to have one wall kznockted out and
currently has a flood light and lights inside. The Public Workts Director
stated this was the first he had heard of this idea. Mr. Herr stated it was
the first time he had brought it up. Discussion followed revolving around
the fact that most existing structures at Riverside Parks would need to be
raised at least two feet to be above flood plain level.
Other Notes and Information
Anticipated FY19 Projects
Items 1, (Repairing 2019 pavement damage) 2, (Review of development
rules) and 3, (updating utility maps) had previously been discussed.
Chairwoman Eaton drew the committee's attention to item 6 (West
Railroad Street coordination) and the update from Mayor Nelson that was
read at the previous weekt's Council worktshop. The Public Worbs Director
stated he had just received an email from Senator Jon Tester's office
regarding TIGR grant and the BUILD Grant Program as possible sources of
funding.
Other Items
Marvin Carter announced that he had been to Senator Tester's office
recently and he was responsible for the email Public Workts Director
Marbegard had received. He also stated that there is a boat parted on
Durland Avenue that has not been in water for the last five years. It was
explained that this was a Police Department issue, not a Public Workts
issue and that the Emergency Services meeting held in the next room had
adjourned some 30 minutes ago. The Public Works Director then
displayed his computer screen on the wall for all to see and sent an email
to the Chief of Police so the entire committee could witness that he passed
the information to the correct people.
7. Announcements
The next meeting will be on lune 17th, 2019 at 6:00 p.m. in the Council
Conference room.
The May 20, 2019 Public Works meeting was adjourned at 7:57 p.m.
Respectfully submitted,
Emelie Eaton
Public Works Chair
May 20, 2019
Public Works Emergency Call -outs since last meeting in March
3-19-19 Water shut off 2414 Lackawanna
3-22-19 Backwash Pond at the Water Plant needed pumping out
3-24-19 Move pump at WTP
4-18-19 Water Turn on at 2618 Topeka
5-8-19 Sewer issue 1220 4t" Ave
City of Laurel, Montana
"On -Call" Engineering Contract
Great West Project No. 2-07128 and 2-14114
Date: May 17, 2019
To: Kurt Markegard, Public Works Director — City of Laurel
From: Chad E. Hanson, PE
Subject: Project Progress Update
G=We
wgng
The following sections summarize the current status and recent progress on active task orders
under our "on-call" engineering contract with the City. Please let me know if you have any
questions and/or would like more information.
Task Order No. 20 — New Water Intake
We submitted the additional documentation for the wetland restoration along the transmission
main route requested by Robert Cole with the Army Corps of Engineers on the City's behalf. We
met with Mayor Nelson, PWD Markegard, and Mr. Cole in our Helena office on March 28'h to
discuss Mr. Cole's review comments in response to the submittal and outlined necessary
additional information that needs to be submitted. We are currently preparing a draft response to
the Army Corps.
Task Order No. 29 — Phase 3 Water System Improvements
COP Construction continues making progress on the project. Both trains of the new plate settlers
are currently on-line and providing temporary treatment of high turbidity water from the river
caused by spring runoff. We have been providing on-site observation as applicable, holding
weekly update meetings with the City, and conducting weekly construction progress meetings
with the City and COP Construction. We have also continued to respond to requests for
information (RFls) from the Contractor and to review submittals as they are received.
1
City of Laurel, Montana
"On -Call" Engineering Contract
Great West Project No. 2-07128 and 2-14114
Task Order No. 38 — Phase 4 Water System Improvements
No work has been performed since the Progress Update Memo dated July 10, 2018, which stated:
The Phase 4 Improvements include lowering the 2003 intake, adding an additional raw water
pump at the WTP, and installing VFDs on all of the large raw water pumps. TSEP and DNRC
grant applications for the project were submitted in the spring of 2016 but fell below the funding
line. The City needs to complete the lowering of the 2003 intake to comply with the Army Corps
permit for the new intake but is undecided on a schedule for the work.
We have done no work on the project and will not until so directed by the City.
2
.mac
KLI
,III, t City of Laurel Project Status Update
May 15, 2019
WWTP Screw Press (KLJ #1804-00120)
Project Manager: Travis Jones/Doug Whitney
Reason for Project: The City's WWTP does not currently have adequate sludge handling equipment,
which has led to overfilling and backup of the drying beds, digesters, and various other WWTP
components. Completion of this project will allow for improved operations and allow for
maintenance of the digesters, which cannot be taken offline until this project is completed.
Project Scope: Design and construction of a new screw press to process WWTP sludge.
Milestones:
• Preconstruction meeting was held December 13th
• Notice to Proceed will be January 7, 2019 (150 -day contract)
Current Status:
• Submittal process is underway.
o Submittals are up to date
o PWTech submittal received 2/11/19
• RFIs are up to date.
• Sludge dewatering is completed, and dewatering subcontractor has moved off site.
• Digester B has been drained and cleaned.
o Repair work on digester B have been completed.
■ Change Order No. 2, for these repairs, has been presented to the Council.
o Digester B has been returned to service.
o Contractor has made a claim for additional pumping.
■ Change Order No. 1 for the undisputed amount has been presented to the
Council. The disputed amount will be negotiated at a later date.
• Digester A has been drained and cleaned.
o Contractor is preparing to sand blast interior.
o Inspection and repairs will take place after sand blasting.
o Recoating of the interior will take place after the repairs are completed.
o Contractor has made a claim for additional pumping. This is currently under review.
• One sludge transfer pump has been removed.
o Both transfer pumps are on site.
o Installation of one of the pumps is underway.
■ A Work Directive for a replacement pressure sensor has been prepared.
• The housekeeping pad for the screw press has been installed.
o The screw press is scheduled for shipment on May 16tH
• The sludge cake discharge line penetration through the wall has been completed.
• The frame work for the roll -off structure is underway.
• The yard piping has been installed and backfilling is underway.
Page 1 of 7
ENGINEERING, REIMAGINED
KL)City of Laurel Project Status Update
May 15, 2019
WWTP Digester Rehabilitation (included in the Screw Press project)
Project Manager: Travis Jones/Doug Whitney
Reason for Project: The City has not taken down the digesters for routine cleaning, inspection, and
repairs for several years. This is due to inadequacy in the sludge handling equipment.
Project Scope: Complete the design and construction administration for the cleaning, inspection,
and repairs of the existing digesters.
Milestones: (see WWTP Screw Press project)
Sanitary Sewer H2S Remediation (KU #1804-00122)
Project Manager: Doug Whitney
Reason for Project: Buildup of H2S within the WW collection system has led to deterioration of
manholes and other system components.
Project Scope: Complete the design and construction administration for the proposed air
injection/diffuser system to address H2S build-up within the system.
Milestones:
• Sewer sampling plan submitted to the City.
• Sewer samples collected on July 19tH
• Results of sewer sampling received on July 30tH
• Analyses of sampling and recommendations for a second round submitted on August 3rd
• Second round of samples collected on August 14tH
• Second round of sampling results received on August 27tH
• Results of second round of sewer sampling received on Sept 25tH
• H2S monitoring: April 2-19, 2019. Completed
• Recommendation from Manufacturer: Was planned for April 30, 2019
• Updated TM with cost estimate: May 17, 2019.
• 60% Plans and Specs: June 6, 2019
• 100% Plans and Specs: June 20, 2019
• Advertise for Bid: June 25, 2019
• Bid Opening: July 16, 2019
• Design of recommended improvements is anticipated for May 2019.
Current Status:
• City has requested that KU proceeds with improvement design independent of future
sampling.
Page 2 of 7
ENGINEERING, REIMAGINED
City of Laurel Project Status Update
May 15, 2019
2018 Pavement Maintenance (KLJ #1804-0012.3)
< KLJ
Project Manager: Carl Jackson
Reason for Project: This continues the City's annual pavement maintenance. As a result of significant
freeze -thaw during the 2017-18 winter, several City streets have significant pavement damage.
Project Scope: The 2018 scope is hot mix asphalt for repaving West 4th Street (6th Ave. - 81h Ave.) and
pothole repairs on West Railroad Street.
Milestones: Construction is complete. Striping was completed May 9-10.
Current Status: The project will be close-out soon.
East 6th Street Improvements (KLJ #1804-00121)
Project Manager: Carl Jackson
Reason for Project: Street reconstruction between 1st Ave. and Wyoming Ave. to address failed
pavement, saturated subgrade conditions and surface runoff improvements. UPDATE: the scope
recently changed to include new water main from Pennsylvania to Wyoming.
Project Scope:
• Grading, paving, parking, and drainage enhancements (minor water main in Wyoming)
• Special Improvement District (sidewalks, driveways), pending approval
• Safety improvements
• Water main from Pennsylvania to Wyoming, including the Wyoming intersection valves.
Milestones:
• Bidding — April/May 2019
• SID creation — May/June 2019
• Construction — completed before August 2019 start of school year
Current Status: Construction phase is about to begin, starting with the preconstruction meeting on
May 21, 2019.
Page 3 of 7
ENGINEERING, REIMAGINED
r* L)City of Laurel Project Status Update
May 15, 2019
LURA Infrastructure Improvements (KU #1804-01309)
Project Manager: Carl Jackson
Reason for Project: Reconstruction and rehabilitation of streets, utilities and various other
infrastructure improvements including Washington Ave., Idaho Ave. and Ohio Ave. generally
bound between E. Main Street and E. 1st Street, as well as E. 1" Street generally bound between
Washington Ave. and Alder Ave.
Project Scope: Preliminary engineering, SID creation, design, bidding and construction.
Milestones:
• Survey & Geotechnical field work — complete
• SID creation — Summer/Fall 2019 (tentative)
• Design & Bidding — ongoing (Phase 1)
• Construction — Phase 1 will be a late-summer/early-fall construction project
Current Status: after meeting with the City leadership on May 3rd it was determined to phase the
project. KU recommended a phasing plan to start with alley sanitary sewers and the north -south
streets for phase 1.
Pavement Management Plan Update (KU #1804-01970)
Project Manager: Bryan Vanderloos
Reason for Project: Develop an updated pavement management plan (PMP) including MDT and City
streets within the Laurel corporate limits. This will be used for prioritizing the City's annual
pavement maintenance projects, along with satisfying MDT's requirement that the City update
its PMP on a regular basis to be eligible for certain future State funding.
Project Scope: Conduct a field inventory by assessing paved streets utilizing the Pavement Surface
Evaluation and Rating (PASER) methodology. A rating of 1-10 will be given to each road segment
based on distresses such as cracks, ruts, potholes, etc. Known roads that have failed pavement
sections and are in disrepair will not be evaluated, and simply given a poor rating.
Milestones:
Final edits are complete, and the final draft was given to Kurt and Matt.
Any final comments from the City are requested by May 28tH
Current Status: Once we have received final comments from the City, we will finalize the report.
Page 4 of 7
ENGINEERING, REIMAGINED
lid City of Laurel Project Status Update
May 15, 2019
2019 Pavement Maintenance (KU #1904-00230)
Project Manager: Bryan Vanderloos
Reason for Project: This continues the City's annual pavement maintenance.
Project Scope: This year's project entails crack seal, chip seal, pavement markings, and other
miscellaneous items on the following streets: South Washington Avenue; 5th Avenue from West
Main Street to West 2nd Street; Cottonwood Avenue from East Main Street to the Ditch
Crossing; East 8th Street from 1st Avenue to Pennsylvania Avenue; and Pennsylvania Avenue
from East 8th Street to East Maryland Lane.
Milestones:
• Bidding — complete
• Construction — April -June 2019
Current Status: Crack sealing was completed April 17th. Contractor Application for Payment No.1 was
submitted to the City. We are awaiting chip sealing in June.
On -Call Professional Services (KLJ #1804-00347)
Project Manager: Carl Jackson
Reason for Project: This contract would enable KU to provide consulting services that are not part of
an approved task order. Generally, this would apply to situations where KU's fees are small
enough that a separate task order is not necessary, or for time -sensitive matters.
Project Scope: Services may include engineering, surveying, planning or government relations. -
Milestones: (as needed)
Current Status:
During the 5/14 bi-weekly meeting KU was asked to evaluate funding options for the future
West Railroad Street reconstruction project. We'll work with City leadership to agree on the
planned approach to this, before proceeding.
Page 5 of 7
ENGINEERING, REIMAGINED
City of Laurel Project Status Update
May 15, 2019
Laurel Planning Services (KU #1804-00554)
Project Manager: Forrest Sanderson
Reason for Project: KU has been retained to provide City of Laurel planning services during the
interim period, while the new City Planner takes on all of the roles associated with the position.
Project Scope: Planning services may include: subdivision, zoning, development, floodplain hazard
management, miscellaneous reviews and other related work. KU will prepare staff reports,
recommendations, and attend meetings upon request.
Milestones: (as needed)
Current Status:
Floodplain Management —Joint Application for improvements at Riverside Park will need to be
completed and a Floodplain Development Permit issued. Post issuance routine inspections and
certifications will need to be performed.
Subdivision Review — Subdivision Review has been transferred to the City Planner. KU Staff are
available to assist as necessary.
Zoning — Zoning has been transferred to the City Planner. KU Staff are available to assist as
necessary.
Riverside Park Campground (KU#1904-00634) —The project will be transferred to Mike Bender
for design and management where Forrest has a regulatory role as City Floodplain
Administrator. Forrest will remain as project liaison between City and Project Manager.
Planning — The Planning Documents of -the City of Laurel either need to be updated to comply
with statutory mandates or have been discussed for updates by Staff or appointed Boards. The
Planning Documents include, but are not limited to:
Growth Policy (Statutory)
Subdivision Regulations (Statutory)
Zoning Regulations (Optional)
Capital Improvements Plan (Optional)
Page 6 of 7
ENGINEERING, REIMAGINED
K QCity of Laurel Project Status !Update
May 15, 2019
Other Notes and Information
Other potential projects have been identified during recent conversations between City staff and
KU. City Public Works staff and KU task leaders meet bi-weekly to discuss current and future
projects. As these are tentative, the timing and extent of KU's services are TBD, unless noted
otherwise.
Anticipated FY19 Proiects
1. Repairing 2019 pavement damage
a. Task order planned for June 4th approval
2. Review of development rules and regulations (related to public works and planning)
a. Task order planned for June 4th approval
3. Updating City utility maps and GIS
a. Task order planned for June 4" approval
b. City would like updated maps and to explore better uses of GIS information.
4. Booster station rehabilitation or replacement (task order forthcoming)
5. Capital Improvement Plan (CIP) assistance — pending further direction from the City.
6. West Railroad Street coordination
7. Water storage tank
Other Potential Future Proiects
1. WWTP Archimedes Screw Rehabilitation
2. Examining engineer review of 3 d Party submittals to City
3. Lion's park grant application assistance
4. On-call government relations
5. West side groundwater remediatiori
Page 7 of 7
ENGINEERING, REIMAGINED
U
m � � W •G 5- 4lit
o
b a N
312
CFFccG
tl
G
In e _ c r a 'zz
0
"
Ri a �C? s y y =€ te a =�€ a' v c a s V ga��a a 1p �• N a G
-to if
cri
®� �` y � C U N N� U J N N fA U� 2 m � i $• 0.' � �. 4 S
J '
_ sf2N-;Liv.asard "T
Zk
C _
i l
a�nr�ev -- n
1 f x I T r mss t (' ' V,
N
_Llr
_I Imo__
/ 4 \ •r � ice._....
9 71
ulomoav�v�ri I g_
�� s fN ,: r i L1
Jf.
1 _ I
2�YV
4F/ 41
St 0776 j T'
TA V i
NIJ � T
r--
U j
f
r"'
IQ
o T2
Ain,
17_ '-
iE
J i
IZ�
'v7
co
m
cr,,
V
U
cn
f -•
N
cr
S1J�Y3dY.LSXId
S
Ili
fn HAAra gig
s t—�
� endo ---
4 37.7X.7 -DHd
N
r HiLsZC i -
'kX,."
y;O
I
JA
lJ HMit—
I I
V
Mu
1
I
r
-�
Ilp
MCIO
---��--� F T eb
L
SIA
Y
¢
�: I
I
■ "" d �Np
i
I
—
N
�
V
1" it
I
I I
j I 1
�
I
I
4'COt
Q a m
�` � � � � �U-5 N f0 � U J N N N U > S [[I yC � $.._�>•g,' 4 4 c
ill !'1111-611 II ill
I
-
S
S a C �
S^
3 8. � t, j S� V� ea t€€ > 4� s
"i ��,•
EO ry R b N g
® S
s N c L) N N U
y�
HAV ao ,cco�
T
--- -- - - �1Y ADY19
-
� � it
I
F�
m.
✓1(
TFF
�.
it
MAY KDL�„tlHSfm -
I+
II
—2 q ra
il I T
—3'—_
3dV VrAWA7dSKhWd .7
r1
nra�raxbnra
1
x
T
� b co
I
U._
. O703 1FT
_, fi
T 17FT—
' k
��
1
►dl
a;
JUI
a
C4
v .19D307
H I
W
I r -T
9AV Mhr
r, U Ol u
• 9AV
12RCP
T
T
i
e
1
U
'00\
c I
N7 oR7yd w cl
a _
Air .dSlL707
u, �� a j ,!➢L � � "451 ��,
JI, P
7.
HAV 7HZPH
7
v -qua --
x
MV
�1
1Hr
j
w
x
�
F
�
a
o u
c€€ a_ T o [
ti
c
� •�- ^� d O
®~ a
...
C
9F`F,'
^
{
Er
L 1
'
J
I Z • 7M1
�
\ �
iV
m 6
A' rmy izE7
I
I
h-%
cn
1
cn
0
1,
s
z
H
{h
5
II
t�
�
o
-7.9X!100 - _�_. _. _.
__•
.4709
1
11i
{
I
I
�I
.__-,- ��.-➢—,K[—���—� . �Y -Gd[ - F-�'Ad➢_f6 Ti _-a�-Q61--1i—���+ F
9AV.
�x x tLLUS.
•� m G. Iii I I I R .i! j ��I Ll
t ty. e y
I TTi U I j'-r'T
II �i I
Tit ,
JU ,��ia s/t .zn I s .it[ atc va" as1 1 ,az a
ri
-LOD i
i in
AO
r
�ONtzNOA
1
F
IN
^Kw r .5
A4m
4e,
.
^I
HfbVHAV
ZSl1707
L
R
mw
a
i lij I I �
- -
HAV ffM \
j
3iVld �I
Y
f l IIIc
---
j
S
�
I TZ F"
�TY
°a
,�
R
_ I I
n
S7?IIS
curt
FE
a
O IO0 A
---oaasc--
lilt
&dY
I
\
s
-
I
L
\
q_
1=;
CforjAO
8 b rq. o n
R y C7 J m N N mfi
a
®� �` h _ � C U N N� U J N N N V 7 2 m p� j. !' $�• �Y . T a e
IJ 7
C
!�
d 0 E Z N � m mv
zi
V
_.VH'ZU
,
i
Qi
miv
j'
T F ,
it 1'
ji
'---- '
Fah t i � C — As. tC .eY[l, a •n• N
o a m W 0 E
S a o
■�
RA VI-ES!
w
.N
:i
.All. J 1 ^ � �
o pq� I I I r — o III
y QA�V727l1Q 1
-„� i
.�
�—I x
—1:7 y Y
e, `1 y I I I I :• 2� III l.1
%IY LS�XHOd 1 — i
,Ili,
T777T
ti
r'
I� -
Its
I IIS I
anv �.
I I
xzs�r --�---
41
i X
011,
G C 01
0 Ci nR d� m N u N m W 5i C
s c€ .. u
r p h E jU N N S U J N N N V> S ��Qyy]
O n
1-4��a�
Ile, �s
y D€ .. d •� €€ q- 9 o a 9 R o ro eo e
woo o..H
h � U N N� U J N f%I N U j 2 m � 2
a
co
It ® rU N N 3 U J (A a N U > 2 `my � � � _ C' " -
V C 0! �7J 'II m N 3 �V� 5 ��. �� •� a' � N
Z I C w 4 s
gg
U o J
I
I n
G
a ,�axvtrvaraa � \ \
e — /X it'"