HomeMy WebLinkAboutPublic Works Committee Minutes 01.22.2019Minutes
Public Works Committee
January 22, 2019 6:00 P.M.
Council Conference Room
Those present:
Kurt Marbegard, Staff Advisor
Emelie Eaton, Chair
Karl Dan Koch
Marvin Carter
Richard Herr
Heidi Sparks
7UMILIAlf
1. The meeting started at 6:00. There was no public in attendance.
2. General items
Review and approve minutes of November 19, 2018 meeting. The
minutes were reviewed. Richard Herr moved the minutes be
approved as written. Heidi Sparks seconded. The motion was
approved. Heidi Sparks questioned whether the minutes be
corrected to state that Bill Mountsier was in attendance. Everyone
agree Bill was not in attendance at the December, 2018 meeting.
3. New Business
a. Emergency Call -outs
Kurt had supplied all attendees with a list of all Emergency Call -outs since
July 1, 2018. The July items had been reviewed at the July Public Works
meeting. The August items had been reviewed at the August Public
Works meeting. The September items had been reviewed at the
September 17th meeting. The October items had been reviewed at the
October 15th meeting. The November items had been reviewed at the
November 19 meeting. The December items had been reviewed at the
December Public Works meeting. Kurt asked the committee if he should
provide only the callouts since the last meeting. It was unanimously
agreed that the committee only wished to see call outs since the lost
meeting. For the January 22, 2019 meeting the following call outs were
listed. December 25, 2018 Crews were sent out to sand the streets due to a
winter storm. December 26, 2018 the Village Lift Station floats were
activated due to grease buildup. On January 19, 2019 there were water
leaks at 1710 Duval in Elena Subdivision and 714 Second Avenue. Both
leaks were service lines leaking at the curb box shut off valves. It became
necessary to call in two City employees and the container site was closed
for this reason. The Second Avenue leak became involved because of
unusually thick cement in the sidewalk around the shut off valve. A
sprinkler head next to the sidewalk was also damaged when crews
attempted to cut the sidewalk to access the shut off. On January 21, 2019
three City employees were called in to do plowing, sanding and shoveling
at City buildings due to a winter storm.
b. February, 2019 Meeting Time
Emelie Eaton stated that because the Public Works Committee is
scheduled to meet on February 18,2019; and because the Public Works
Director had stated at last month's meeting that he no longer wished to
meet on holidays, and because he had further stated to Chairwoman
Eaton that he had plans to be gone for a large portion of the week of
February 18, 2019; she was making a motion to cancel the February 18,
2019 Public Works meeting. That motion was seconded by Richard Herr.
Discussion followed regarding whether there would be anything new to
report to the committee that could not wait until the March 18th meeting.
It was unanimously agreed that the February 18, 2019 meeting was
cancelled and the committee would next meet March 18, 2019. Bill
Mountsier joined the meeting and was brought up on what had been
discussed.
4. Old Business
a. KL) and Great West Engineering Reports
Kurt had supplied copies of the January 18, 2018 Project Progress Update
from Great West.
Task Order No 26. New Water Intake
As was stated previously, the leak was fixed. The report states Great West
is covering costs for this repair.
Task Order No. 29 Water System Improvements
Regarding putting lettering on the new water storage tank by Riverside
Park south of Laurel, Kurt stated that the Mayor had agreed to add the
cost of putting "Laurel" in 4' white lettering on the cobalt blue tank. Kurt
confirmed that the final cost on this addition will be an additional $2,300
and was well within the budget.
Great West's plans for the covered sedimentation buildings called for the
gas pipes running parallel to Highway 212 be rerouted to heat the new
buildings. MDU had surveyed the situation and stated they did not wish to
dig their lines out of what is apparently a collection of pipelines in that
area. They informed the City that if the City wished to reroute the line it
would be their responsibility. The City is now assessing who would be
willing to do this work and what the cost would be.
KLJ's January 15, 2019 City of Laurel Project Status Update was next
reviewed. The Screw Press/Digester Rehabilitation project is underway.
Crews are pumping down the water so the area can be cleaned and
repairs made. They are leaving solids in the sedimentation beds to dry.
Kurt showed pictures of the beds filled 3"-4" full of the materials taken out
to dry. It is presently too cold to haul the materials, since the moisture has
only frozen and not evaporated or run off. This is creating something of a
backup in the process as the beds are filling and there is still more to be
taken away. K. Dan Koch inquired if the material couldn't be used as
fertilizer. Kurt explained that while Glacier Gold, a gardening fertilizer
that can be found in a local hard ware store, does come from the Kalispell
sedimentation basins, there are extensive DEQ requirements that have to
be met to make the product safe to be distributed to the public. Currently
Laurel has pumped out roughly 300,000 gallons and Billings uses the
dried product as cover over the trash at the County landfill.
Kurt did state that he felt there would be a problem when crews start to
drain the digesters. He stated that millions of dead snails from a build up
elsewhere were likely collected at the bottom of the first digester. He also
stated that the second digester leaks. No one would know the extent of
the damage or be able to estimate the cost until it was drained. He stated
that crews expected to need 7 to 10 days to finish this part of the project.
They had started on Saturday, January 19th So it was expected there would
be answers soon.
The H2S Remediation issue. Nothing discussed
Archimedes Screw Rehabilitation. Nothing discussed.
East 6th Street improvements.
The scope of this project changed with the City requesting off-street
parking within Thompson Park; and installing a new water main within
East 6th Street to provide looping for side street connections. KLJ had
completed looking at the water main on December 3rd and had
determined that the water pressure was sufficient and there was no need
to loop. This was paid for out of Water Enterprise Funds.
The issue of off street parking had been reviewed and KLJ had provided
some estimates for cost. The issue of putting a parking lot where the tennis
courts now sit was eliminated because of fear of foul balls hitting cars. If
the City were to put in parking east of the shelter, where the ice skating
rink was many years ago, it would cost approximately $150,000 or $7,500
each for the roughly 20 parking spots that could be built. This money
would have to come out of the General Fund because creating a parking
lot in the park does not fall into the guidelines of uses for street
improvement monies or Gas Tax dollars. KL) has stated that changing to
diagonal parking along East 6th Street would provide 16 parking spots and
save the City a considerable amount. Kurt stated that the consensus now
is to change East 6t" Street to diagonal parking.
Pavement Maintenance. Nothing discussed.
LURA Infrastructure Improvements
Kurt explained that the mayor had proposed LURA fund improvements to
Washington Avenue; Idaho Avenue and Ohio Avenue between East Main
Street and East First Street. The Mayor is now considering delaying this
issue for three years. Emelie Eaton inquired what reaction the Railside
Diner had to this change of direction. Kurt responded that the Railside
Diner wishes to expand their building and the plan is to build to the
sidewalk so they are anxious to have improved streets and possibly
diagonal parking for their patrons. Emelie Eaton inquired whether the
brewery was still going to pay for their own curb, gutter and sidewalk
improvements. Kurt stated that once the brewery's owners heard that the
City was planning to make improvements to the sidewalks, street, curb
and gutters, they withdrew their plans to finance the project for their
business and the area will remain with the gravel scraped away.
Pavement Management Plan
It is expected that a draft form of this report will be available in February
and the committee can review it in March. Public Works Director
Marhegard stated that all streets on the south side are earmarked for
complete rebuild. KU is still gathering information as it learned that those
streets designated as Urban Routes have to have information gathered
beyond the City limits. Kurt stated that the report that KL) provides will
give cost estimates which are expected to be between $60 and $70 million
to complete all improvements. Heidi asked where the money comes from
to make these improvements. Kurt stated that it comes from the Gas Tax
Fund and Pavement Maintenance Fund. He stated that TIGER grants are
available but he felt that it was impossible to get any federal grant money
when Laurel was so close to Billings and we would be competing with
them for funding because the grants were based on how much traffic used
any given street. Heidi disagreed with his, stating that if the City applied
for a TIGER grant for SW 4th Street and included the 2,000 additional
employees every three years during a turn around the numbers would
look good. Kurt brought the web site up on his computer and showed the
committee two small Montana towns that had received TIGER grants. The
web site https://www.transportation.gov/BUILDgrants gives the specs needed to apply
for the BUILD -TIGER Discretionary Grants.
Marvin Carter left the meeting at 6:55 stating he had another meeting to
attend in five minutes.
On -Call Professional Services -Nothing was discussed
Laurel Planning Services
Kurt stated that on January 19th the Laurel Planner job had been offered
to a planner by the name of Nick now located in New Hampshire.
Other Notes and Information -nothing was discussed
b. Update on West Railroad Street
Kurt stated that the state had reviewed the joint County/City of Laurel
request to place West Railroad Street on the list of state projects.
Consequently, the state reviewed the materials submitted to it and had
met with City staff earlier in the day. The state had said it could not
proceed with the project until the City proved it had the match funding
for the project as it was submitted. The City stated it had reserved
approximately $4 million and that $200,000 was added to it annually
which would bring the total to roughly $4.7 million in five years when
construction is expected to begin. The state said the match needed to be
between W$7 million in today's dollars and costs would go up as time
passed. The state recommended changing the scope of the project and
either replacing Railroad Street from 11t Avenue to 5th Avenue or from 5th
Avenue to Sth Avenue. In the earlier meeting the CAO and Treasurer had
urged the Mayor to hold off on the project. Committee members were
hugely disappointed in this report and will be inquiring at the next
workshop what steps the City plans to take to proceed and re-evaluate
and not let this project die once again. Kurt stated that the state was
looking at improving West Railroad to "Urban Standards" which meant
dealing with underground utilities, which were more extensive that the
Public Works Director was aware of, and making it at three lane road.
S. Other Items
No one had any other items.
6. Announcements
There were no announcements.
The January 22, 2019 Public Works meeting was adjourned at 7:07 p.m.
Respectfully submitted,
Emelie Eaton
Public Works Chair
City of Laurel, Montana
"On -Call" Engineering Contract
Great West Project No. 2-07128 and 2-14114
Date: January 18, 2019
To: Kurt Markegard, Public Works Director — City of Laurel
From: Chad E. Hanson, PE
Subject: Project Progress Update
The following sections summarize the current status and recent progress on active task orders
under our "on-call" engineering contract with the City. Please let me know if you have any
questions and/or would like more information.
Task Order No. 26 — New Water Intake
We submitted the additional documentation for the wetland restoration along the transmission
main route requested by Robert Cole with the Army Corps of Engineers on the City's behalf. We
have reviewed the Corps' response to the additional documentation but are waiting on direction
from the City before preparing a response.
Task Order No. 29 — Phase 3 Water System Improvements
COP Construction continues making good progress on the project. The new basins are mostly
poured, and the plate settlers are scheduled for installation beginning today. We have been
providing on-site observation as applicable, holding weekly update meetings with the City, and
conducting weekly construction progress meetings with the City and COP Construction. We have
also continued to respond to requests for information (RFIs) from the Contractor and to review
submittals as they are received.
Task Order No. 38 — Phase 4 Water System Improvements
No work has been performed since the Progress Update Memo dated July 10, 2018, which stated. -
The Phase 4 Improvements include lowering the 2003 intake, adding an additional raw water
City of Laurel, Montana
"On -Call" Engineering Contract
Great West Project No. 2-07128 and 2-14114
pump at the WTP, and installing VFDs on all of the large raw water pumps. TSEP and DNRC
grant applications for the project were submitted in the spring of 2016 but fell below the funding
line. The City needs to complete the lowering of the 2003 intake to comply with the Army Corps
permit for the new intake but is undecided on a schedule for the work.
We have done no work on the project and will not until so directed by the City.
K L
City of Laurel Project Status Update
January 15, 2019
WWTP Screw Press (KU #1804-00120)
Project Manager: Travis Jones/Doug Whitney
Reason for Project: The City's WWTP does not currently have adequate sludge handling equipment,
which has led to overfilling and backup of the drying beds, digesters, and various other WWTP
components. Completion of this project will allow for improved operations and allow for
maintenance of the digesters, which cannot be taken offline until this project is completed.
Project Scope: Design and construction of a new screw press to process WWTP sludge.
Milestones:
• Preconstruction meeting was held December 13th
• Notice to Proceed will be January 7, 2019 (150 -day contract)
Current Status:
Submittal process is underway.
Contractor is mobilizing on site.
Dewatering sub -contractor has mobilized and planning to start dewatering operation on
Friday the 18tH
WWTP Digester Rehabilitation (concurrent with above Screw Press project)
Project Manager: Travis Jones
Reason for Project: The City has not taken down the digesters for routine cleaning, inspection, and
repairs for several years. This is due to inadequacy in the sludge handling equipment.
Project Scope: Complete the design and construction administration for the cleaning, inspection,
and repairs of the existing digesters.
Milestones: (As needed)
• Will be concurrent with WWTP Screw Press
Current Status:
• Once the interior of the digester is cleaned and can be evaluated for needed restoration, a
construction change order and engineering amendment may be required.
Page 1 of 6
ENGINEERING; REIMAGINED
R ��� K L
:A]J1 City of Laurel Project Status Updatee-o, ,
r„
January 15, 2019
Sanitary Sewer H2S Remediation (KLJ #1804-00122)
Project Manager: Travis Jones/Doug Whitney
Reason for Project: Buildup of H2S within the WW collection system has led to deterioration of
manholes and other system components.
Project Scope: Complete the design and construction administration for the proposed air
injection/diffuser system to address H2S build-up within the system.
Milestones:
• Sewer sampling plan submitted to the City.
• Sewer samples collected on July 19tH
• Results of sewer sampling received on July 30tH
• Analyses of sampling and recommendations for a second round of sewer sampling
submitted to the City on August 3`d
• Second round of samples collected on August 14tH
• Second round of sampling results received on. August 27tH
• Results of second round of sewer sampling received on Sept 25tH
• Design of recommended improvements is anticipated for May 2019.
Current Status:
• City has requested that KU proceeds with improvement design independent of future
sampling.
WWTP Archimedes Screw Rehabilitation (KU #TBD)
Project Manager: Travis Jones
Reason for Project: The grouting around the existing screw pumps is wearing down, which makes
the pumps less efficient in the transfer of wastewater.
Project Scope: Complete the design and construction administration for the rehabilitation of the
existing screw pumps.
Milestones: (As needed)
Current Status: (KLJ Contract Pending)
• No significant updates since previous status report.
Page 2 of 6
ENGINEERING, REIMAGINED
KLCity of Laurel Project Status Update; ,
January 15, 2019XX
East 6th Street Improvements (KLJ #1804-00121)
Project Manager: Carl Jackson
Reason for Project: Street reconstruction between 1st Ave. and Wyoming Ave. to address failed
pavement, saturated subgrade conditions and surface runoff improvements. UPDATE: the scope
recently changed to include new water main from Pennsylvania to Wyoming.
Project Scope:
• Grading, paving, parking, and drainage enhancements (minor water main in Wyoming)
• Special Improvement District (sidewalks, driveways), pending approval
•, Safety improvements
• Water main and valve replacements in Wyoming intersection.
Milestones:
• Survey and preliminary design — complete
• Final design — Winter 2018/2019 (ongoing)
•, Bidding — February/March 2019 (tentative)
• SID creation — April/May 2019
• Construction — completed before August 2019 start of school year
Current Status: Road design is underway. Water main will be looped by adding a new 8 -inch line
between Pennsylvania and Wyoming. Off-street parking (in Thompson Park) is pending City
review of available funding; KU is not incorporating off-street parking in the current design.
2018 Pavement Maintenance (KLJ #1804-00123)
Project Manager: Carl Jackson
Reason for Project: This continues the City's annual pavement maintenance. As a result of significant
freeze -thaw during the 2017-18 winter, several City streets have significant pavement damage.
Project Scope: The 2018 scope is hot mix asphalt for repaving West 4th Street (6th Ave.- 8th Ave.) and
pothole repairs on West Railroad Street.
Milestones: Construction is substantially complete. Striping will need to wait until Spring 2019.
Current Status: (no progress to report until spring re -start)
Page 3 of 6
ENGINEERING, REIMAGINED
rl
�I RS'E L AJC
City of Laurel Project Status Update KLI
January 15, 2019
LURA Infrastructure Improvements (KLJ #1804-01309)
Project Manager: Carl Jackson
Reason for Project: Reconstruction and rehabilitation of streets, utilities and various other
infrastructure improvements including Washington Ave., Idaho Ave. and Ohio Ave. generally
bound between E. Main Street and E. 1st Street, as well as E. 15Y Street generally bound between
Washington Ave. and Alder Ave.
Project Scope: Preliminary engineering (survey, geotechnical and CCN inspections), SID creation,
design, bidding and construction.
Milestones:
• Survey & Geotechnical field work — complete
• Preliminary Engineering — February 1, 2019
• SID creation — Spring 2019
• Design & Bidding — pending results and completion of Preliminary Engineering
• Construction — will occur during 2019 construction season
Current Status: Preliminary engineering is nearly complete, after which time the scope of the 2019
project will be discussed with the City. It is possible the project will be built in phases (TBD).
Pavement Management Plan Update (KLJ #1804-01970)
Project Manager: Bryan Vanderloos
Reason for Project: Develop an updated pavement management plan (PMP) including MDT and City
streets within the Laurel corporate limits. This will be used for prioritizing the City's annual
pavement maintenance projects, along with satisfying MDT's requirement that the City update
its PMP on a regular basis to be eligible for certain future State funding.
Project Scope: Conduct a field inventory by assessing paved streets utilizing the Pavement Surface
Evaluation and Rating (PASER) methodology. A rating of 1-10 will be given to each road segment
based on distresses such as cracks, ruts, potholes, etc. Known roads that have failed pavement
sections and are in disrepair will not be evaluated, and simply given a poor rating.
Milestones:
• Field Inventory (pavement condition assessment) — November 1, 2018
• PASER analysis and draft PMP (report) —January 15, 2019
• Finalize PMP (report) based on City review and feedback — February 14, 2019
• Attend City Council meeting to discuss the plan after February 141H
Page 4 of 6
ENGINEERING; REIMAGINED
RrL City of Laurel Project Status Update
January 15, 2019 ,
Current Status: A draft report review meeting was held Monday, January 14 and KLJ is in the process
of making edits before resubmitting for final City comment.
On -Call Professional Services (KU #1804-00347)
Project Manager: Carl Jackson
Reason for Project: This contract would enable KLJ to provide consulting services that are not part of
an approved task order. Generally, this would apply to situations where KLJ's fees are small
enough that a separate task order is not necessary, or for time -sensitive matters.
Project Scope: Services may include engineering, surveying, planning or government relations.
Milestones: (as needed)
Current Status: No services were provided last month.
Laurel Planning Services (KU #1804-00554)
Project Manager: Forrest Sanderson
Reason for Project: KU has been retained to provide City of Laurel planning services during the
interim period, while the search for the new City Planner is ongoing.
Project Scope: Planning services may include: subdivision, zoning, development, floodplain hazard
management, miscellaneous reviews and other related work. KU will prepare staff reports,
recommendations, and attend meetings upon request.
Milestones: (as needed)
Current Status:
Floodplain Management — minimal activity this month.
Subdivision Review—The primary efforts during the past month include Iron Horse Phase 2,
Regal Park, Brester Minor, Russel Minor and Robertus Ag Exemption.
Zoning—Answered several questions on Zoning compliance. Prepared a staff report and
attended the Planning and Zoning Commission meeting on the Annexation and Initial Zoning
Request for Goldberg LLP prepared by Performance Engineering.
Planning — primary overall activity included meeting attendance and office work related to
Planning and Zoning Commission consideration of the Goldberg LLP Annexation and Initial
Zoning, along with bi-weekly meeting with City and KU staff.
Page 5 of 6
ENGINEERING, REIMAGINED
City of Laurel Project Status Update ,`\
January 15, 2019
Other Notes and Information
Other potential projects have been identified during recent conversations between City staff and
KLJ. City Public Works staff and KU task leaders meet bi-weekly to discuss current and future
projects. As these are tentative, the timing and extent of KLJ's services are TBD, unless noted
otherwise.
Anticipated FY19 Projects
1. Booster station rehabilitation or replacement (task order forthcoming)
a. Anticipated as a spring 2019 project.
2. Capital Improvement Plan (CIP) assistance — pending further direction from the City.
3. Planning (task order amendments forthcoming)
a. Review of development rules and regulations (related to public works and planning)
b. Growth Policy update
4. Annual Pavement Maintenance (crack/chip seal, other repairs TBD)
a. This will be annual; tentatively scheduled forbidding in spring 2019
5. Railroad Street coordination
a. A joint resolution between the City and County is pending.
6. Water storage tank evaluation
a. Timis coordinating inspections of the tanks in Spring 2019, which will help
determine the scope of work, which may include external and internal coating.
7. Updating City utility maps and GIS
a. City would like updated maps and to explore better uses of GIS information. The
task order is pending clearer understanding of the scope by both KLJ and the City,
which will come from future discussions.
Other Potential Future Projects
1. Examining engineer review of 3`d Party submittals to City
2. Lion's park grant application assistance
3. On-call government relations
4. Riverside Park improvements
5. West side groundwater remediation
Page 6 of 6
ENGINEERING, REIMAGINED
October 15, 2018
Public Works Emergency Call -outs since July 1, 2018
7-1 Elm Lift Station Alarm
7-11 110 Yellowstone Sewer Complaint
8-5 H2O Break North of Nutting Park
8-9 Replace manhole lid East Main Street
8-16 Water turn on 201 3rd Avenue
August Meeting
8-18 Digester Sump Pump Fail
8-23 Water leak at 110 % 7th Avenue
September Meeting
9-3 H2O problem 9214"' Avenue
9-6 H2O turn on 1055 Montana Ave
9-8 H2O leak South 8th Ave
9-15 Murry Heights Water Booster pump noise
October Meeting
9-24 Elm Lift Station Failure
10-10 Elm Lift Station Failure- Alarm was set off by AT&T update. We changed
the alarm to go to water treatment plant.
November Meeting
10-16 Water turn on at 2509 Atchison Dr.
10-28 Village Lift Station backup floats activated
11-7 Sanding
11-11 Water Leak 8th Ave. and East 91h Street Townhomes
11-12 Clean Streets S.E. 4Th Street Glass shattered across road
11-16 Sand Streets for Ice and Snow Storm
December Meeting
11-28 Sewer Plant Power Failure
12-6 PLC to the Blower Building failed- needs replaced
January 22, 2019 Meeting
12-25-2018 Sanding Streets
12-26-2018 Village Lift Station Floats activated
1-19-2019 Water Leaks at 1710 Duval and 714 2nd Ave. Service lines leaking at
curb box shut off valves. Called in two people and closed container site.
1-21-19 Called in three people to deal with the snow storm. Plow, Sanding and
Shoveling City buildings.