HomeMy WebLinkAboutDepartment of Commerce - 8th AvMontana DeJ~artment of Transportation J~m Lynch, D~rector
2701 Prospec! Avenue Brian Schweitzer, Governor
PO Box 20 I001
Helena MT 59620-I001
December 8, 2006
Mr. Kenneth E. Olson, Jr.
Mayor of Laurel
814 5th Ave.
Laurel, MT 59044-1906
Subject: STPU 6905 (1)
8th Ave. ~ Main to 7th -Laurel
CN 3927
Dear Mayor Olson:
Attached is a letter from Engineering Inc. that discusses the potential costs and benefits
of modifying the current project design. This topic was discussed at the Plan-in-Hand
held in November. A narrower and lower roadway typical section was analyzed by the
Consultant and summarized in the Design Modifications Memorandum. The proposed
project benefits and associated engineering fees are summarized in the letter. Although
this project is managed through the Department of Transportation, this project uses Urban
funds and therefore requires your input on this potential design change. Please review the
letter and provide a response at your earliest convenience. We will not proceed until we
receive a reply from the City. Thank you for your attention to this project issue.
Please feel free to contact Mark Studt at 444-9191 if you have any questions.
TJC :mis 2927_Mayor. DOC
copies: Copies with all
Tom Martin P.E., Consultant Design Engineer
Brace H. Barrett., District Administrator - Billings
Steve Klotz, Laurel Public Works Director
Bryan Vieth, Design Supervisor, Consultant Plans Section
Consultant Design Project File
Consultant Design Bureau An Equal Opporlunity Employer
Phone: (406) 444-6200 Engineering Division
Fax: (406) 444-6253 TTY. (800) 335-7592
Web Page: www, mdt mt.gov
November 14, 2006
Mr. Mark Studt, PE
Consultant Design Bureau
Montana Department of Transportation
P. O. Box 201001
Helena MT 59620-1001
Reforence:
Design Moditleations Memorandum
8th Avenue - Main to 9th - Laurel
STPU 6905 (2) Control No. 3927
E.I. No. 99137
Dear Mark:
As discussed at the Plan-in-Hand (PIH) conducted on November 2, 2006, Engineering,
Inc. was given the task of determining the cost and benefits, if any, that could be realized
by lowering the proposed roadway profile and reducing the proposed street and boulevard
widths from the current design to a narrower footprint. This narrowing was suggested
during PIH and would include narrower travel lanes, parking lanes, and boulevard
widths. The option for lowering the roadway evolved when a Montana Department of
Transportation (MDT) comment surfaced during the Scope of Work Report review
pea'iod, which requested that the asphalt thickness in the typical section be increased from
90 mm to 120 mm and MDT's new structural coefficients be incorporated. The result
was that the overall thickness of the surfacing section was reduced by 240 mm (9 inches).
Since conception, the roadway grades have been driven largely by the need to provide
vertical separation between the proposed road surface and the proposed storm drain
trunkline which caused the proposed finished surface of the roadway to be elevated
higher than the existing roadway. This resulted in fill slopes, impacts to personal
property, nuroe~ous construction permits, and the need to reconstruct portions of
driveways, private sidewalks, fencing, and other items.
Benefits that can be realized from lowering the roadway and narrowing the footprint
include radueing the fill slope depths and widths, a reduction in the number of
construction permits, providing more area adjacent to the right-of-way (R/W) for utility
placement, and a reduction in impacts to existing features such as fencing and
landscaping. This will also help us with reducing the area of R/W needed between 2nd
and 4th Streets West where R/W acquisition is necessary for this project.
1300Norll~1~ohslechW~y' Billings.~l 591C'2' Pl~one(406)6~6-5255' Fax(406)656-0967' ww'.,,'e,ginccom
Mt'. Mark Studt, PE
November 14, 2006
Page 2
Below is an itemized list of cost savings and project benefits that could be realized by
lowering the roadway profile and by narrowing certain typical section dimensions.
Cost Savings:
Based on discussion at tile Plan-in-Hand meeting conducted November 2, 2006,
for the project, we analyzed the effects of reducing the roadway typical section
fi`om its current hack-of-curb to back-of-curb width of 16.0 m to 12.3 m. We
have calculated that the savings would be approximately $140,650.00 (difference
between attached estimates). This savings is due to reduced typical section
surfacing quantities, as well as reduced storm drain inlet piping lengths.
A noticeable savings will be realized by decreasing the amount of reconstruction
of private sidewalks and driveways. We estimate that the quantity ofcenerete
estimated for these features ceuld be reduced by approximately 380 sq m ~
$59.75/sq m (current estimate) = $22,722.93. Adding the contingencies, ere. fi`om
above raises this to approximately $34,400.00.
In addition to these construction cost savings, we have estimated the savings in
R/W. We estimated that there will be 16 fewer construction permits (per R/W
Plans...Lots I l, 12, 13, 15, 23, 25, 26, 31, 32, 33, 34, 36, 38). At $500.00 per
construction permit (estimate, based on $300.00 minimum per Brent McCaan),
this would be another $8,000.00 savings.
The R/W requirement between West 2nd Street and West 4th Street on the west
side of 8th Avenue could be reduced by an estimated 440 sq meters (4,735 sq
feet) for an estimated cost savings of perhaps $10,000.00 (average of around
$2.00/sq f~ based on ad. jaeent lot pficea).
Additional savings in RFC/could be realized by avoiding having to replace trees,
landscaping features, sprinkler heads, etc.. that would be damaged and require
replacement due to new sidewalk installation under current design. The
associated cost savings is estimated at $2,500.00.
The original project cost for fencing was approximately $45,000.00, including all
the contingencies. We estimate that the cost would by reduced by approximately
$7,500.00, since less existing fencing would be directly impacted by construction.
Mr. Mark Studt, PE
November 14, 2006
Page 3
Pl~oiect Benefits:
Engineering, Inc. looked at the utility conflicts, primarily power poles, and underground
utilities that might lie near the existing R/W line. It does appear that several utility poles
and some of the fiber optics will no longer be in conflict iftha roadway is narrowed near
the south end oftha project, but a cost savings was not assessed due to the unknowns.
Narrowing up the typical section would provide more mom between the R/W limits and
the back of sidewalk for utilities to oecapy.
We have taken a quick look at the effect of decreasing the imparvious surface by
narrowing the roadway, and it appears that it has a relatively insignificant effect on the
overall design peak flow; it is estimated that a reduction of approximately 2.5 cfs can be
realized by reducing the asphalt width of 8th Avenue. This reduction would be beneficial
to the project, since it allows the design to incorporate more free-board (distance from top
of water surface at maximum design elevation to top of basin berms) in the detention
ponds by allowing an increase in the allowable outfloTM from the upstream detention
basins as they are currently designed. Therefore, it is not anticipated that the reduced
width will create the need for smaller trunkline pipe, but narrowing the roadway still does
have a net project benefit in terms of hydraulic design.
En~ineerina Fees:
We have assessed the design efibrts to pursue both lowering the roadway and narrowing
the roadway, and estimate our design services would approximate $70,000.00 or so.
Most of the work remaining for this project is still within Engineering, Ine.'s scope of
work and is, therefore, not included as part of fha $70,000.00. The estimate is only for
those eft-offs to lower and narrow the roadway from the current design.
Summary
The net effect of lowering the roadway profile and reducing the roadway typical section
dimensions is an estimated $133,000.00 savings (construction costs + RfC/+ incidentals
- design services) to the project, Supporting documentation is provided to this
memorandum as attachments.
Sincerely, /f
Kirk Spalfling, Pmj~'ct Manager
/dml
encl
Montana Department of Transportation Page
~ F~ Preliminary Estimate
Project 'Ri{e: 8th Avenue - Mair~ Io 9th - Laurel Prepared by: Kirk Spalding
PreJact Number, STPU 6905(2) Dale: September 22, 2006
PmJecl Lenglh: 1,08 km Locallon: Yelrowslona Co~'~'
Des. Super Approval: Type er'Work: ,
Project Cord Number:. 3927 D A Approval:
eU~UUUUL3~' 838 I:ENCE'CHA1N UNKst~btolaT bi $40.00 $21.S20.0~ $gI~20.00
PmJ~ Len,q~h
IAVera~e Prelect Finish Top Wtdtll m
Cost per ~]lameler Uses Ca~lan T~
106
Montana Department of Transportation
B~ pm=., Preliminary Estimate
Jan0$-Jul06
Projec~TIf~e: Prepared by: T. Kelsey
Project Numbec Date: November 6, 2006
Project Lenglh: Location: Laurol- Yellowstone County
Des Super Approval: Type of Work:
Subject: Ori___glnal Typical QuanUties D A Approval:
Page 1 of I
~mDun ~ Unit Prices ~ll',i'(~Us~
[Paih]3527Ealimate Smeller Typical Seclion xls
Bid Prices
JanOS.JulO$
Montana Department of Transportation
Preliminary Estimate
Project Title: Prepared by: T. Kelsey
Project Number. Date: November 6, 2006
Project Length: Localion: Laurel - Yellowstone County
Des Super Approval: Type o[ Work:
Subject: Smaller Typical Quanti~/Chang~ D A Approval:
Page I of 1