The Public Works Committee meeting was called to order at 6:45pm on Monday, January 22, 2024, by
Committee Chair, Heidi Sparks.
Members Present: Heidi Sparks- Chair, Iry Wilke- Vice -Chair, Jodi Mackay, Jessica Banks, Emelie;Eaton
Others Present:
Public Input: Emelie stated she watched the Council meeting from last week, January 16. She stated she
appreciated the background and explanation provided by Council President Sparks around West Railroad. She
added context that West Railroad is an Urban Route because it comlects to the county and helps bring in county
residents into the city. Should also bring up the annexation of South Pond/Lions Park and determine if West
Railroad from 8t" to the overpass was annexed with that.
General Items
1. Iry Wilke nominated Heidi Sparks as Chair, No additional nominations. Iry moved to approve, Jodi
second, Motion carried 4-0. Iry nominated Jodi Mackay. No additional nominations. Iry moved to
approve, Heidi seconded- Motion carried 4-0
2. Approval of Minutes from December 18, 2023. Iry made a motion to approve the minutes of December
18, 2023. Motion was seconded by Jodi. Motion carried 4-0 to approve the minutes.
New Business
Emergency Call Out Report- Report attached
4. KLJ Report- Report attached
Old Business:
Other Items
5. Jodi stated that she talked with the owner of Red Rooster regarding parking in the area. The question
had been raised around a timed -parking sign, such as 15 -minute parking. Jodi received information
from Kurt on how to proceed with that. Jodi would like to revisit the conversation of parking in the
downtown area and the possibility of putting in diagonal parking down by Pennsylvania.
Announcements
Next Meeting will be Monday, February 26, 2024, at 6:45pm in Council Chambers
Meeting adjourned at 7:37pm
Emergency Overtime Callout List 1/1/2024 TO 6/30/2024
Maintenance Shop 406-628-4773 City Dispatch 406-628-8737
Response Code X In Column Not accepting Overtime /NA = Not Available /Y = Responding /B=Phone Busy
Employee Name Telephone
Shop Callout 1-6
1-6 1-7 1-13 1-13 1-14 1-15 1-16
Brian Kline AlINA
NAI NAI
Kevin Budge
g
Jay Hatton
2 NA2
Keith Guy
3 NA3
Wade Spalinger
4 NA4
Brandon Gonzales
5 NA5
Aaron Fox
6 NA6
Troy Clifton
7 NA7
Joel Barnhardt
8 Y8
Water and Sewer Callout -b
1-6 1-7 1-13 1-13 1-14 1-15 1-16
Justin BakerY4
3 na3 y4 3 3
Kevin Hoffman 4 3
2 nal na2 na2 NA2
Daniel Nauman l
nal nal nal nal NAI
Tom Burwell 2
y4 y4 3 y4 Y4
Elm Lift Station 628-7773 Village Lift Station 628-5918 Dial 9 after tone to acknowledge alarm
Wastewater Treatment Plant -628-6474 Autodailer- 628-4866
Response Code NO= In 1st Column Not accepting Overtime / NA = Not Available / Y = Responding
Employee e
Thomas Henry
Cindy Caswell
ii
Corey Nicholson
Norman Stamper
Water Treatment P
Response Code NO= In 1st Column Not accepting Overtime / NA = Not Available t Y = Responding
Employee Telephone
HP Nuernberger
Dylan Ceaser
Josh Sawyer
Sam Waggoner
Joe Waggoner
TJ Worbel
Daniel Waggoner
CABLE TV down Tim Johnson 698-6254
Matt Wheeler Cell# 208-1885
10ne Call Locate -1-800-424-5555 (City Job # 25663)
Kurt Markegard Cell# 860-5785 Hm 208-2356 SCHESSLER 628-4221 HESTON 281-0811
INW ENERGY 1-800-896-7862 LUMPY 406-860-7890
Advanced Pump 406-586-1700
ICentury Link 1-800-573-1311 Shop 628-7707Jeff 694-9097
GORDAN ACE ELECTRIC 406-860-5464
NorthwestPipe 252-0142 - Larry E. 656-2856
MDU 1-800-638-3278 /MDT 252-4138
Pace Construction 252-5559 (sewer backups)
MDT Supervisor Tom 655-7903/Kyle 446-2622SanitarySystemOverilows
call DEQ withing 24 hours at406-444-3080
Call out - Date and Incident Location
1-7 Sanding Streets 1-6 Water leak
1-6 Emergency Locate
1-13 Structure Fire
1-13 Elm Lift Station Alarm
1-14 H2O shut off
1-15 H2O shut off
1-16 Emergency Locate
City of Laurel Project Status Update
January 15tj; 2024 ` 3;
Reason for Proiect: Existing City water Tank needs to be recoated on the inside and can't happen
until City has a backup storage supply. They also have needs for upgrades to their upper pressure
zones. See previously approved Water System PER and City of Laurel CIP. This project looks at
funding opportunities and provides grant writing services from multiple sources
Proiect Scope: To research funding alternatives, create packages for submittal, and assist City in
finding monies for completing the future water tank and upper pressure zone improvements for the
City of Laurel
Current Status:
• Task Order Signed by City on 12/13/23
• Met with EDA to discuss Funding on 1/9/24
5th to 71h Sewer Line Replacement
(KLJ # 23+04-01231)
Reason for Proiect: Refurbishment of an 8" sewer line between 7th Avenue and 61h Avenue
and a 10" sewer line between 6th Avenue and 5th Avenue in the alley way between 1st Street
and Main Street in Laurel, Montana. The existing sewer line experienced several collapses
last year.
Proiect Scope: To replace approximately 363 lineal feet of 8" and 383 lineal feet of 10" and
will include the update of 3 manholes and associated surface replacement.
Current Status:
• Work Order Signed by City in September 2023
• Survey scheduled for week of October 16th, 2023
• Base Drawing created and Working on preliminary design
• Preliminary Plans and EEOC sent to City on 12.14.23
Splash Park Installation
(KLJ #2204-01898)
Reason for Proiect: To Replace the existing pool with a.,splash pad recreation area.
Proiect Scope: To Construct a splash Pad at the site of the existing City pool.
Page 1 of 3
ENGINEERING, REIMAGINED
i 1City of Laurel Project Status Update
s-�- %� MJanuary
Current Status:
• Work Order Signed by City in January 2023
• DPHHS Approved Permit on 5/25/23
• Preconstruction Meeting held on 9/15/2023
• Construction to start on Monday 918/2023
• Change order sent to Contractor on 10/30/2023
• Ultimate completion date of April 28th -2024
• Change Order Executed on 1.02.2024
2022 Pavement Maintenance Project (4th Street Reconstruction)
(KLJ #2104-00862)
Reason for Project: To provide yearly maintenance and improvements to the City of Laurel Roads
Network.
Proiect Scope: Miscellaneous annual pavement maintenance design, bidding and construction in
locations throughout the City of laurel
Current Status:
Substantial Completion reached Date is 10/11/23
Final Completion date was 11/16/23
Closeout/Reconciliation Change Order approved by Council on 1/9/24
Laurel Planning Services (KLJ #1804-00554)
Reason for Proiect: KU has been retained to provide City of laurel planning services as needed.
Proiect Scope: Planning services may include; subdivision, zoning, development, floodplain hazard
management, miscellaneous reviews and other related work. KU will prepare staff reports,
recommendations, and attend meetings upon request.
Current Status:
• Zoning Regulations Update.
o Draft regulations sent to City April 1111, 2023
o Zoning Map approved by Commission on August 16th, 2023
o Staff Recommendation to Zoning Commission to occur on December 20th, 2023
o Back to Planning Board Meeting on 1/17/23
• Downtown Parking Study. — On hold per City Instructions
• City -County Grown Policy Update was requested at the August 16th meeting
o Weekly meetings occurring in October.
Page 2 of 3
ENGINEERING, REIMAGINED
City of Laurei Project Status Update
January 15th, 2024
o KUupdating maps asrequested byCity Planner
o Back tuPlanning board meeting un1/17/Z3
1(< L)
,17
Other potential projects have been identified during recent conversations between City staff and KU.
City Public Works staff and KU task leaders meet monthly to discuss current and future projects. As
these are tentative, the timing and extent of KU's services are TBD, unless noted otherwise.
Anticipated FY24 Projects
1. 7mStreet reconstruction
2. RkerfrontPark walking trail —OnHold Until further notice
3. Downtown Parking Study —Toprogress following zoning completion
4. Overlay of 121h Street between Valley Drive and 11t Ave. Task Order sent to City.
a. City will put together service agreement for Hordhvestocomplete.
S. Bulk Water Sales Station — City identified project tooccur in2U24
Page 3of3