HomeMy WebLinkAboutWater Task Force/Reservoir/Water Plant Minutes 09.14.1995• WATER PLANT STEERING COMMITTEE September 14, 1995 11:00 A.M. Members Present: Dave Mosser and associate, Dave Michael, Jim Flisrand, John (Refinery), Chuck Rodgers, Albert Ehrlick Discussion on overall project, including construction additives. Intent of this meeting yyas to finalize cost estimate( Copy of final estimate enclosed). Motion by Flisrand and seconded by Ehrlick to accept Morrison and Meriele's cost estimate as presented, Motion carried. Steering Committee recommends the City Council accept preliminary cost estimate to allow the development of the rate structure and design process. Meeting adjourned 12:15 P.M. is • n OPINION OF PROBABLE COST i FOR: CITY OF LAUREL DATE: SEPTEMBER 12, 1995 - REVISION RE: LAUREL WATER TREATMENT IMPROVEMENTS Page 1 PROPOSED ITEM MODIFICATIONS CHLORINE CONTACT BASINS - clearwell structure $197,000 - 24" finish water to clearwell $18,000 - 30" pipe - clearwell to high service pum j $59,000 - 24" piping - existing tank to clearwell $28,000 BACKWASH/CLEARWELL PUMP STATION BACKWASH/FILTER TO WASTE MODIFICATIONS - backwash piping $222000 - piping gallary addition $527000 - interior gallary piping $174,000 • - color code piping $10,000 CHEMICAL SYSTEM - see construction additives - chemical building and equipment $344,000 - paved turn around delivery area $5,000 SEDIMENTATION BASINS - see construction additives - common wall- open and closed basins $25,000 - resurface floor slab $31,000 - repair top of common wall sed/flocc $25,500 - resurface sloped walls $22,500 FLOCCULATION BASINS - see construction additives - rebuild outflow $9,500 - replace skimmer baffles $8,800 - spot repair separation wall $5,000 - spot repair slide gate wall $22100 PLANT FACILITY IMPROVEMENTS - backwash basin addition $30,500 - chemical mixing chamber $50,000 - direct filtration piping $457500 $302,000 $337,500 $258,000 $349,000 $104,000 $25,400 $126,000 Page 2 PLANT AUTOMATION/ELECTRICAL $210,000 - electrical/controls $150,000 - emergency generator and switchgear $60,000 4.0 MGAL TANK - see note 1 $257,800 - interior painting $198,800 - exterior overcoat seal $55,000 - safety ladder $4,000 CONCRETE RESERVOIR - see note 1 $196,000 - interior lining $68,000 - cover (aluminum truss/fabric cover) $128,000 BERNHARDT ROAD EXTENTION $1012000 18" WATER MAIN $306,000 - S. 4th/hwy To 5th S./Main - MRL route Estimated Probable Const. Cost $2,5722700 Contingency @ 5% $128,635 Total Probable Construction Cost $2,701,335 Construction Cost $2,701,335 Engineering Fees $461,000 Legal and Administrative Fees $100,000 BASE PROJECT COST $37262,335 CONSTRUCTION ADDITIVES - includes 5%b contingency $370,900 - overlay slide gate wall - floc basin $1,800 - overlay separation wall- sed/floc $51600 - stabilize baffle walls - sed basin $8,500 - chlorine scrubber - see note 2 $152,000 - additional 1400 if 18" waterline $182,000 - replace hydraulic gates - sed/floc $21,000 Engineering Fees $10,000 - for additional 14001f of waterline TOTAL PROJECT COST WITH ADDITIVES $3,643,235 Tr Page 3 NOTE 1: Construction Options - Estimated cost increase or decrease from the alternate shown in the project cost estimate. CONCRETE RESERVOIR COVER - steel roof ($23,000) - concrete roof $22,000 - fiberglass roof $921000 - aluminum roof $97,000 - floating cover ($80 ,000) - rigid floating cover ($43,000) CONCRETE RESERVOIR INTERIOR - shotcrete $1,000 - hypolon liner $3,000 4.0 MGAL STEEL TANK - new aluminum roof $170,000 - sandblast/repaint exterior $250,000 NOTE 2: If the city of Laurel decides that the chlorine scrubber will not be included in the scope of work, then $152,000 can be subtracted from the total probable cost. 0