WATER PLANT STEERING COMMITTEE
September 14, 1995
11:00 A.M.
Members Present: Dave Mosser and associate, Dave Michael, Jim Flisrand, John
(Refinery), Chuck Rodgers, Albert Ehrlick
Discussion on overall project, including construction additives. Intent of this meeting
yyas to finalize cost estimate( Copy of final estimate enclosed). Motion by Flisrand and
seconded by Ehrlick to accept Morrison and Meriele's cost estimate as presented, Motion
carried.
Steering Committee recommends the City Council accept preliminary cost estimate to
allow the development of the rate structure and design process.
Meeting adjourned 12:15 P.M.
is
•
n
OPINION OF PROBABLE COST
i FOR: CITY OF LAUREL
DATE: SEPTEMBER 12, 1995 - REVISION
RE: LAUREL WATER TREATMENT IMPROVEMENTS
Page 1
PROPOSED
ITEM MODIFICATIONS
CHLORINE CONTACT BASINS
- clearwell structure $197,000
- 24" finish water to clearwell $18,000
- 30" pipe - clearwell to high service pum j $59,000
- 24" piping - existing tank to clearwell $28,000
BACKWASH/CLEARWELL PUMP STATION
BACKWASH/FILTER TO WASTE MODIFICATIONS
- backwash piping $222000
- piping gallary addition $527000
- interior gallary piping $174,000
• - color code piping $10,000
CHEMICAL SYSTEM - see construction additives
- chemical building and equipment $344,000
- paved turn around delivery area $5,000
SEDIMENTATION BASINS - see construction additives
- common wall- open and closed basins $25,000
- resurface floor slab $31,000
- repair top of common wall sed/flocc $25,500
- resurface sloped walls $22,500
FLOCCULATION BASINS - see construction additives
- rebuild outflow $9,500
- replace skimmer baffles $8,800
- spot repair separation wall $5,000
- spot repair slide gate wall $22100
PLANT FACILITY IMPROVEMENTS
- backwash basin addition $30,500
- chemical mixing chamber $50,000
- direct filtration piping $457500
$302,000
$337,500
$258,000
$349,000
$104,000
$25,400
$126,000
Page 2
PLANT AUTOMATION/ELECTRICAL $210,000
- electrical/controls $150,000
- emergency generator and switchgear $60,000
4.0 MGAL TANK - see note 1 $257,800
- interior painting $198,800
- exterior overcoat seal $55,000
- safety ladder $4,000
CONCRETE RESERVOIR - see note 1 $196,000
- interior lining $68,000
- cover (aluminum truss/fabric cover) $128,000
BERNHARDT ROAD EXTENTION $1012000
18" WATER MAIN $306,000
- S. 4th/hwy To 5th S./Main - MRL route
Estimated Probable Const. Cost $2,5722700
Contingency @ 5% $128,635
Total Probable Construction Cost $2,701,335
Construction Cost $2,701,335
Engineering Fees $461,000
Legal and Administrative Fees $100,000
BASE PROJECT COST $37262,335
CONSTRUCTION ADDITIVES - includes 5%b contingency $370,900
- overlay slide gate wall - floc basin $1,800
- overlay separation wall- sed/floc $51600
- stabilize baffle walls - sed basin $8,500
- chlorine scrubber - see note 2 $152,000
- additional 1400 if 18" waterline $182,000
- replace hydraulic gates - sed/floc $21,000
Engineering Fees $10,000
- for additional 14001f of waterline
TOTAL PROJECT COST WITH ADDITIVES $3,643,235
Tr
Page 3
NOTE 1:
Construction Options - Estimated cost increase or decrease from the alternate shown
in the project cost estimate.
CONCRETE RESERVOIR COVER
- steel roof ($23,000)
- concrete roof $22,000
- fiberglass roof $921000
- aluminum roof $97,000
- floating cover ($80 ,000)
- rigid floating cover ($43,000)
CONCRETE RESERVOIR INTERIOR
- shotcrete $1,000
- hypolon liner $3,000
4.0 MGAL STEEL TANK
- new aluminum roof $170,000
- sandblast/repaint exterior $250,000
NOTE 2:
If the city of Laurel decides that the chlorine scrubber will not be included in the scope
of work, then $152,000 can be subtracted from the total probable cost.